Regulatory deadlock keeps renewables investors in Croatia on seven-year hold

Croatian Chamber of Commerce regulatory framework deadlock renewables investors seven years

Photo: Croatian Chamber of Commerce

Published

February 8, 2023

Country

Comments

0

Share

Published:

February 8, 2023

Country:

Comments:

0

Share

The Croatian Chamber of Commerce (HGK) has warned that investors in renewable energy have been waiting seven years for a regulatory framework to install wind farms and solar parks. The new laws since 2021 haven’t changed a thing because bylaws are missing and new investments were halted, it pointed out.

Croatia adopted the Law on the Electricity Market and the Law on Renewable Energy Sources and High-Efficiency Cogeneration in 2021. The new framework envisages the issuance the energy approval. Under interim provisions, the government invited developers to submit projects and received 216 applications, but investors have been complaining the process is too slow.

According to HGK’s Association of Renewable Energy Sources, all the deadlines for the adoption of bylaws for the two laws have expired.

All deadlines for the adoption of bylaws have been missed

The rules on connection to the transmission network and the rules on connection to the distribution network have been drafted. But for several months the documents have been sitting in the Croatian Energy Regulatory Agency (HERA) and the Ministry of Economy and Sustainable Development to be given a green light.

The decree on the public calls for energy approvals, a key document for developing a project, is more than a year late, the association said.

Also, the price of grid connection hasn’t been determined even though the deadline expired five months ago. The investors also await the changes in the regulation on encouraging the production of electricity from renewable energy sources and high-efficiency cogeneration.

Čović: It is not possible to develop projects even on private land

The adoption of the new Law on the Electricity Market has completely stopped investments, even on private land, and it will be like that until the bylaws are adopted, the association’s President Ivo Čović said.

He stressed time was wasted during the energy crisis, arguing that energy independence should be at the top of the priority list.

Instead of importing expensive electricity, Croatia could export it, thanks to the great potential of renewables, Čović added.

Instead of investments in new power plants, the country spent EUR 600 million on imports

The representatives of the association noted that in the first eight months of 2022, Croatia paid EUR 592 million for electricity imports.

The money could have been used to install 600 MW in renewable power plants, however the country currently has only 140 MW in solar power plants.

Instead of investing them in photovoltaic facilities and producing domestic electricity, the funds were lost, said Ivan Strunje, a member of the council of the association.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Slovenia coal plant TES close already within three years

Slovenia’s coal plant TEŠ could close already within three years

06 May 2024 - Slovenian Prime Minister Robert Golob said coal plant TEŠ and its accompanying mine may end operations before the expected closure in 2033

data-center-microsoft-renewable-capacity

Microsoft to power AI, cloud services with 10.5 GW of new green energy plants

06 May 2024 - The deal between Microsoft and Brookfield is almost eight times as big as the largest single corporate power purchase agreement ever signed

Greece launches first auction for Guarantees of Origin

Greece schedules first auction for guarantees of origin

06 May 2024 - The Greek renewable market operator, DAPEEP, said the country's first auction for guarantees of origin would take place on June 26

Croatia-HEP-pumped-storage-hydropower-plant-Blaca

Croatia’s HEP preparing to build pumped storage hydropower plant Blaca

06 May 2024 - HEP Group's pumped storage hydropower plant Blaca would have a capacity of 498 MW in turbine mode and 489 MW in pumping mode