Power utility EAC developing solar park projects with Church of Cyprus

Power utility EAC solar park Church of Cyprus

Photo: Dimitrisvetsikas1969 from Pixabay

Published

February 17, 2022

Country

Comments

comments icon

0

Share

Published:

February 17, 2022

Country:

Comments:

comments icon

0

Share

After getting the approval for four solar power plants of 16 MW in total, the joint venture of the Holy Archdiocese of Cyprus and Electricity Authority of Cyprus is working on 14 more units with an overall capacity of 68 MW.

The Department of Environment received an environmental impact assessment (EIA) study for a group of photovoltaic plants valued at EUR 70 million, Philenews reported. The projects are being developed by a firm set up by the Church of Cyprus and the state-owned Electricity Authority of Cyprus (EAC), which holds a 49.99% stake.

The proposal was published for public consultation until March 16.

The joint venture plans to build 14 solar power plants with a combined capacity of 68 MW in the mountainous area of Achera next to the Agios Ioannis Malountas village in the Nicosia district. The document reveals construction work is expected to begin next year and last until mid-2025.

Achera area becoming solar hub

The Holy Archdiocese of Cyprus and EAC earlier got approval for four photovoltaic units of 16 MW in total, the article adds. The projects are also located in Achera in the central part of the country.

The joint firm said in the study that the 14 units would be connected to the grid at different points. The area covered in the document spans 195 hectares while the lots intended for solar parks take up 174 hectares.

The arrays of solar panels are planned to cover almost 100 hectares. Twelve hectares are intended for the transmission network and accompanying installations should take up 1.1 hectares, leaving 60 hectares unused.

In the 195-hectare area, 12% is a protected zone. The plan includes EAC’s substation. The estimated lifespan of the projects is 25 years from the commission date.

The nearest inhabited areas are the villages of Meniko to the north and Agios Ioannis to the east, both 2.2 kilometers from the nearest sites for the solar power plants.

Risks for birds

According to the document, mitigation measures would reduce the small and moderate negative effects expected during construction and the moderate and significant impacts that are seen during the operation of the photovoltaic units. A significant impact is expected on the bird species in the area.

The Department of Agriculture said it disagrees with the project, noting that the area is cultivated and moderately fertile, the report adds.

Of note, Greece’s Central Macedonia regional authority is using European funds for the installation of solar power plants of 2.6 MW in total at 17 out of 20 monasteries in Mount Athos,

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

montenegro necp law on cross border exchange electricity natural gas sahmanovic

Montenegro adopts National Energy and Climate Plan

10 December 2025 - The government adopted the National Energy and Climate Plan and the draft law on cross-border exchange of electricity and natural gas

Greek authorities launch electricity market probe

Greek authorities launch electricity market probe

10 December 2025 - HCC and RAAEY began a double probe into the Greek electricity market for potential manipulation

eu energy system 2050 net zero scenarios costs hitachi study

Energy system based on renewables is cheapest solution to achieve net zero by 2050 – study

10 December 2025 - The study, produced by Hitachi Energy for WindEurope, has mapped out the total system costs of five energy scenarios

Bulgarian Hydrogenera electrolyzer order Volkswagen

Bulgarian firm Hydrogenera gets electrolyzer order from Volkswagen

10 December 2025 - Hydrogenera will integrate its electrolyzer with a gas burner at Volkswagen Poznań's automotive factory in western Poland.