EPBiH’s three-year business plan envisages EUR 850 million in investment

EPBiH-business plan

Photo: Pixabay/EdWhiteImages

Published

January 5, 2021

Comments

comments icon

0

Share

Published:

January 5, 2021

Comments:

comments icon

0

Share

State power utility Elektroprivreda Bosne i Hercegovine (EPBiH) has adopted a three-year business plan that envisages investments of some EUR 850 million and electricity output at about 18,433 GWh, as well as an increase in renewable energy production and purchases against 2020. The priorities also include launching construction on small hydropower plants (SHPPs) on the Neretvica river during 2021, continuing the construction of hydropower plant (HPP) Vranduk, and creating conditions for further work on the Vlašić wind farm, HPP Janjići, and solar projects.

The 2021-2023 business plan of one of the three state-owned power utilities in Bosnia and Herzegovina also envisages completing the construction of the Podveležje wind farm and bringing it online on March 1, 2021.

Podveležje is expected to generate 100 GWh of electricity in 2021

Works on Podveležje, its first wind farm, were launched in May. According to EPBiH’s business plan, the 48 MW wind farm, located near the city of Mostar, is projected to generate 100 GWh of electricity in 2021, and 120 GWh each in 2022 and 2023.

Wind farm Vlašić, also with an installed capacity of 48 MW, is expected to produce 115 GWh a year. Its construction will be financed with loans from the European Investment Bank (EIB) and the German development bank KfW.

According to earlier reports, EPBiH also plans to develop 200 MW in solar power capacities at its closed coal pits.

Investment in coal-fired power plants is also planned

EPBiH’s three-year business plan also involves investment in coal-fired power plants, including building unit 7 and overhauling unit 6 at thermal power plant (TPP) Tuzla, as well as an overhaul of unit 7 at TPP Kakanj.

At the same time, EPBiH plans flue-gas desulfurization projects at TPP Tuzla’s power generation unit 6 and TPP Kakanj’s unit 7, while its strategic objective for the upcoming period is to bring the thermal power plants into line with the National Emission Reduction Plan (NERP), according to a statement from the company.

The business plan also envisages a EUR 35.8 million capital injection into coals mines and the procurement of 13.9 million tons of coal.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

solar output snow winter

Record solar output in Romania pushes power prices into negative territory

02 March 2026 - On Friday at 11:39 a.m., commercial solar output, excluding prosumers, reached 2,048 MW, while demand stood at slightly over 6,000 MW

Power imports dropped almost at zero for Greece in January

Power imports in Greece drop to nearly zero in January

02 March 2026 - Greece saw the balance of electricity exchanges with neighboring markets change rapidly during the last couple of years. It became a net exporter.

serbia hemofarm rooftop solar plant vrsac

Hemofarm commissions one of largest rooftop solar plants in Serbia

27 February 2026 - The largest rooftop solar plant in Serbia is on the buildings of polymer products maker Peštan

bih republic of srpska loans garanties power plants distribution grid petar djokic

Republic of Srpska plans EUR 204 million in loans for power plants, grid

27 February 2026 - The Republic of Srpska is ready to issue guarantees for BAM 400 million (EUR 204.5 million) for coal power plants and the distribution grid