Greece tests Peloponnese-Crete link – world’s longest undersea AC cable

Greece tests Peloponnese Crete link world's longest undersea AC cable

Photo: Admie

Published

December 25, 2020

Country

Comments

comments icon

0

Share

Published:

December 25, 2020

Country:

Comments:

comments icon

0

Share

The world’s longest alternating current cable system is functional, as the first power interconnection between Crete and mainland Greece was successfully tested. The link with the Peloponnese peninsula is 174 kilometers long, of which 132 kilometers are on the seabed.

Independent Power Transmission Operator, also known as Admie or IPTO, said the 24-hour test drive of its submarine interconnector between Peloponnese and Crete, the biggest island in Greece, was successful. Italy’s Prysmian laid 132 kilometers of the link under the Sea of Crete. The remainder of the 174 kilometers runs underground on both sides, making it the longest high voltage alternating current (HVAC) cable system in the world.

It is the longest undersea triplex cable interconnection with cross-linked polyethylene (XLPE) insulation, while it has the biggest depth on the planet as well, as much as 1,000 meters, the state-controlled firm said. There are only a handful of longer direct current submarine cables in the world.

European, Greek government funds included in Peloponnese-Crete interconnector project

A second cable, to the west from the first one, is expected to be installed in the first quarter. The overall 150 kV project is worth EUR 356 million. It can cover as much as 34% of the power demand in Crete. Admie secured a twenty-year loan of EUR 178 million from the European Investment Bank in May of last year, while the interconnection is also backed with government funds.

The cable’s capacity will match a third of demand in Crete

The cable connects Megalopolis in central Peloponnese with Heraclion, the biggest city on the island. The subsea portion goes from Chania in Crete to Neapoli Voion.

Cablel and Fulgor laid the underground part and Terna built the substation in the Peloponnese and upgraded the Chania unit. The project spans eight cities.

Greece’s biggest island to be connected to Cyprus

Admie’s Chairman and CEO Manos Manousakis said it is now certain that the “energy blockade of Crete” would be lifted and that the system was switched on two years after the first contracts were signed. The interconnector will help the development of renewables in Greece’s largest island.

Of note, Admie is working on a EUR 1 billion project for an even longer cable, between Crete and the Attica peninsula, via its Ariadne Interconnection subsidiary. It is scheduled to come online in 2023 and boost the capacity to supply the island entirely. Crete is currently dependent on fossil fuel for its electricity.

The EuroAsia Interconnector should link Israel with Europe via Cyprus and Crete.

Admie’s investment plan for the next ten years is worth EUR 4.4 billion. The transmission system operator has just picked Mytilineos for the reconstruction of the Koumoundourou high-voltage center. The project is worth EUR 46 million. The transmission hub will be connected both with Megalopolis and the future Crete-Attica line.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

montenegro memorandum mou bgen bef sahmanovic branislava jovicic

Montenegro’s Ministry of Energy seals strategic partnership with Balkan Green Energy News

03 April 2026 - The Ministry of Energy and Mining of Montenegro and Balkan Green Energy News signed a memorandum of understanding

battery energy storage data center AI bess

Global energy storage installations surge 61.3% in 2025, with AI demand set to drive growth

03 April 2026 - In 2026, the world is expected to add a further 353.4 GWh of energy storage capacity, driven by demand from AI data centers

NGEN commissions 9 4 MW Tesla Megapack battery storage system in Poland

NGEN commissions 9.4 MW Tesla Megapack battery storage system in Poland

03 April 2026 - Poland got its second utility-scale battery storage installation, as NGEN built a 9.4 MW facility, consisting of Tesla Megapack 2XL units

anze predovnik adex bsp electricity market interview

Predovnik: EU – Western Balkans electricity market coupling expected in early 2028 or beginning of 2029

03 April 2026 - We discussed electricity markets, and CBAM with Chairman of the Management Board of ADEX Group and CEO of BSP Southpool Anže Predovnik