Kosovo*, Air Energy 2 sign agreements for 100 MW in wind farms, solar power plant

kostt wind farm solar park air energy

Photo: KOSTT

Published

December 23, 2020

Country

Comments

comments icon

0

Share

Published:

December 23, 2020

Country:

Comments:

comments icon

0

Share

Developer Air Energy 2 will install two wind farms and a solar power plant with a combined capacity of 99.6 MW.

Kosovo’s transmission system operator KOSTT and Air Energy 2 have signed the agreements for the connection of the three facilities to the transmission system.

The power plants will be online by the end of 2024

The start of the construction of the power plants is planned for 2021, while they are expected to be commissioned by the end of 2024, according to KOSTT.

CEO of KOSTT Mustafa Hasani and director of Air Energy 2 Kenan Guler have signed the agreements for the connection of wind farms PE Kamenica-1 (34.8 MW) and PE Kamenica-2 (34.8 MW) and solar power plant PS Kamenica-3 (30 MW) to the grid.

Kosovo* currently has only one operational wind farm – Kitka

The three renewable energy projects will be connected to the 110 kV transmission network via a 110 kV line of about 25 kilometers, which will be connected to substation 110/10 (20) kV Gjilan 5.

Two wind farms are under construction

Kosovo* has only one wind farm – Kitka, with an installed capacity of 32.4 MW, which will be expanded by 20 MW. The power plant is developed by Air Energy, a subsidiary of Güriş Holding from Turkey.

Two wind farms are in the pipeline. Bajgora, with an installed capacity of 105 MW, is expected to come online in April, while Bondcom Energy Point is developing the Budakova wind power plant project of 46 MW.

* This designation is without prejudice to positions on status and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

EUSEW 2026 to focus on a clean, secure and competitive Energy Union

EUSEW2026: Focus on clean, secure, competitive Energy Union

25 November 2025 - The European Sustainable Energy Week (EUSEW), Europe’s largest annual gathering dedicated to renewables and energy efficiency, will take place in June 2026

Enery to start building Europe's largest solar power plant in Romania

Enery to start building Europe’s largest solar power plant in Romania

25 November 2025 - Enery is preparing to break ground on a solar park of 750 MW in Romania – it would currently be Europe's largest

greece Mesochora hydropower ppc relocation study ministry

PPC receives funds for stalled Mesochora hydropower project 

25 November 2025 - Public Power Corporation has received funds to speed up its Mesochora hydropower project, stalled for 24 years

croatia social climate policy plan EU ets 2 marija vuckovic

Croatia drafts EUR 1.68 billion Social Climate Plan

25 November 2025 - The funds would be obtained from the auctions of emission allowances in the European Union and Croatia under the EU ETS 2