Authors: Ivan Gazdić, Partner and Igor Đorđević, Attorney-at-Law, CMS Belgrade

On 15 March 2020, the state of emergency was introduced in Serbia due to the COVID-19 situation, which entitles state authorities to impose a broad spectrum of short-term restrictions and different measures. What do these measures mean for the future of renewable energy projects in Serbia?

What the PPA says

Under Article 27 of the model Power Purchase Agreement for the renewables (PPA), if due to force majeure one party is unable to fulfill its obligations under the PPA, it must inform the other party accordingly.

Force majeure, under the PPA, is any unforeseeable or unavoidable event that is beyond the control of the parties and includes in particular the state of emergency, among other things.

In the event of force majeure, the PPA should remain in force, but its legal effects must be deferred during force majeure.

Upon termination of force majeure, the PPA will continue, and the period of validity of the PPA will be extended for the period of force majeure.

A party affected by force majeure will notify the other party both of the occurrence of force majeure, and the time when it is able to continue fulfilling its obligations under the PPA.

Force majeure and impossibility of performance

Should the performance of an obligation by one party in a bilateral contract become impossible due to an event not attributable to either party (e.g. due to force majeure), the other party’s obligation will cease too, while the party that performed part of its obligation can request restitution (as per Article 137 of the Serbian Obligations Act).

Impossibility of performance causes the automatic cessation of the parties’ obligations under the law (i.e. no formal termination of the agreement is required).

Impossibility of performance needs to be permanent. Otherwise, if impossibility will last for a certain period, rules on the impossibility of performance and its consequences cannot apply.

To conclude, the state of emergency as a force majeure event should not constitute a permanent impossibility of performance of the PPA (given that the PPA is concluded for a 12-year incentive period). Hence, the PPA should survive such a force majeure event. However, in accordance with the PPA, if the offtaker is unable to fulfill its obligations under the PPA due to force majeure, the legal effects of the PPA will be deferred during force majeure (e.g. during the state of emergency) until the force majeure event ceases to exist. In this case, the period of validity of the PPA will be extended for the duration of the force majeure event.

But does the state of emergency in Serbia truly make the offtaker unable to fulfill its assumed obligations? And will any of the parties be entitled to ask for amendments to the PPA due to the state of emergency?

Force majeure and changed circumstances

After the conclusion of any contract, unpredictable circumstances might emerge:

  • making the performance of the obligation of one party difficult; or
  • the purpose of the contract cannot be realised (any longer).

In this “changed circumstances” scenario, performance is still possible, but very difficult or the purpose of the contract is lost. In both cases, it must become evident that the contract no longer meets the expectations of the contracting parties, and that generally speaking it would be unjust to maintain its validity as it stands.

The changed circumstances as described above entitle the party having difficulties in performing its obligations to request termination of or amendments to the contract, as per Article 133 of the Serbian Obligations Act.

If, for example, the offtaker is afraid of not having regular payments of electricity, including collection of special fees for renewable energy sources (RES) electricity generation, from end consumers due to the state of emergency, does it mean that the offtaker will not be able to fulfill its obligations under the PPA? Or will this potential risk of non-liquidity only make the fulfillment of the offtaker’s obligations more difficult, but not impossible? Could the offtaker offer a lower purchase price for electricity or a moratorium to RES power producers due to the state of emergency? And if so, for how long?

In this scenario where end consumers are not paying the electricity bills in a timely manner, such non-payment, in order to be relevant, should be significant or continuing, causing unpredictable economic losses for the offtaker due to which the payment of the prices under the PPAs’ feed-in tariffs becomes onerous. Nevertheless, the risk of collection of debt under electricity bills seems predictable. Hence, any ordinary delay in bill payments should not interfere with the PPA.

However, it may be too early to raise the argument of offtaker non-liquidity, especially given that feed-in tariffs are regulated and guaranteed under the law.

On the other hand, offering a lower price to electricity producers at this moment raises questions whether this PPA would still be bankable or if the PPA would (with such reduced prices) severely alter the expectations of the RES investors and their sponsors. Given that the most important RES projects are funded through structured project financing with a clear stipulation of the financial covenants, the price cutting would likely result in the occurrence of an event of default towards lenders under the facility agreements. (Offering a moratorium during the state of emergency – giving offtaker’s authorisation to postpone payments – would make more sense in this scenario than a price reduction.)

It goes without saying that unilateral amendments of the PPA by the offtaker are not possible. If the offtaker offers amendments of the commercial terms to power producers, and they decline the offer, the offtaker could file a lawsuit for termination of the PPA. Even if hypothetically the matter goes to court, it would still be possible to work out amendments to the PPA during the proceedings instead of termination.

In our view, any premature and unilateral moves by the offtaker would potentially lead to the misuse of the force majeure event that damages legal certainty and could result in massive claims and disputes initiated by RES investors, which would endanger Serbian renewable energy commitments to the EU.

For more information on this eAlert, contact your regular CMS advisor or local CMS experts Ivan Gazdic and Igor Djordjevic.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

ems ai transmission

EMS plans to use AI in construction approvals

21 November 2024 - EMS has decided to automate its construction approval procedure by introducing state-of-the-art AI solutions

IPTO ENCS cybersecurity grid

Greece’s IPTO joins European Network for Cyber Security

21 November 2024 - The European Network for Cyber Security (ENCS) has announced that IPTO has officially joined the network as a full member

montenegro gvozd epcg nordex agreement

Montenegro’s power utility EPCG begins construction of Gvozd wind farm

21 November 2024 - Wind farm Gvozd will be the first large-scale power generation facility to be built by EPCG in more than 40 years

Bulgarian waterworks firm installs in pipe hydropower generator

Bulgarian waterworks firm installs in-pipe hydropower generator

21 November 2024 - A waterworks and sewerage firm in Bulgaria produces electricity using an in-pipe hydropower device in a supply line