Dravske elektrarne Maribor plans EUR 65 million investment in wind farms

Photo: Dravske Elektrarne Maribor (HSE)

Published

December 13, 2019

Country

Comments

comments icon

0

Share

Published:

December 13, 2019

Country:

Comments:

comments icon

0

Share

Slovenia’s power utility Dravske Elektrarne Maribor (DEM) plans to invest EUR 65 million in three wind farms – Ojstrica, Paški Kozjak, and Rogatec. The installed capacity of the wind farms would be 46 MW with an expected output of 122 GWh per annum.

Currently, Slovenia has only two wind turbines, with the production of 6 GWh in 2018, compared with 249.6 GWh generated by the country’s solar power plants, 125 GWh by biomass plants, and 112.3 GWh by biogas plants.

The estimated generation of wind farms would be enough to cover 4% of households’ electricity consumption

Dravske Elektrarne Maribor, 100% owned by state power utility Holding Slovenske Elektrarne (HSE), is operating with almost 600 MW in installed capacity of eight large hydropower plants (HPPs) on the Drava River, five small hydropower plants (SHPPs) and four solar power plants. Annual power generation is enough for one quarter of Slovenia’s electricity needs, while the estimated generation of wind farms would be enough to cover 4% of households’ consumption.

All three projects are far from final investment decisions

Based on measurements, the three areas with wind power potential were identified in the area of ​​northeastern Slovenia, namely Ojstrica, Paški Kozjak and Rogatec, but all three projects are far from final investment decisions, and much activity remains to be done before it is clear that wind farms can be constructed, DAM said on its website.

The national zoning plan for the Ojstrica wind farm is under development

The national zoning plan for the Ojstrica wind farm is under development. According to the company, the plan is currently in the phase of verification of the spatial and environmental details, which will be followed by studies on the possibility to construct the wind farm.

At the end of October, the Ministry of the Environment and Spatial Planning announced that it is working on national zoning plans for eight wind farms including Ojstrica.

The company said the two other projects are in the phase of obtaining guidelines for spatial planning.

Andrej Tumpej, managing director, said that as a state-owned company, DAM cares about achieving the commitments made by Slovenia regarding the production of electricity from renewables.

The company has experience and knowledge to install wind farms without harming the environment, he added.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Green for Growth Fund financial impact targets 2023

Green for Growth Fund tops its financial, impact targets in 2023

15 July 2024 - The Green for Growth Fund kept mitigating climate change and promoting sustainable economic growth last year in its 18 markets

IRENA La Camera renewables must grow higher speed scale

IRENA’s La Camera: Renewables must grow at higher speed, scale

12 July 2024 - IRENA's Director-General Francesco La Camera warned of ongoing patterns of concentration in geography in renewables deployment as well as against complacency

green steel electric vehicles study transport environment

Switching to green steel would add just EUR 8 per electric vehicle by 2040

11 July 2024 - Switching to 40% green steel would add just EUR 57 to the sticker price of an electric vehicle in 2030, according to an analysis by T&E

Albania declares eight winners at 300 MW solar power auction

Albania declares eight winners at 300 MW solar power auction

10 July 2024 - The lowest bid at Albania's solar power auction came in at EUR 39.7 per MWh, against a starting level of EUR 59.97 per MWh