State power utility Elektroprivreda Srbije (EPS) has put in operation the fifth overhauled unit at HPP Đerdap 1, adding 30 MW of installed capacity to Serbia’s biggest hydropower plant.

After the commissioning of the fifth overhauled unit, there is only one more unit left to be revitalized, and that job should begin next year, according to Milorad Grčić, acting general manager of EPS. The overhaul of HPP Đerdap 1’s generators is being performed by Russian company Siloviye Mashiny, which signed the 10th addendum to its agreement on the project with EPS in mid-2018.

The overhaul has extended the lifespan of the five units by another four decades

Aleksandar Antić, Serbia’s mining and energy minister, said that the overhaul has extended the lifespan of the five units by another four decades, adding that HPP Đerdap 1 is of exceptional significance since it accounts for more than half of the output of the country’s hydropower sector.

In its 47 years of operation, HPP Đerdap 1 has produced some EUR 14 billion worth of electricity, while the annual output of a single unit is worth between EUR 40 million and EUR 50 million. Once the sixth generator is revitalized, the power plant’s total additional capacity for the production of clean energy will rise to 180 MW, according to a statement from EPS.

The planned overhaul of Đerdap 2 will add a further 50 MW to EPS’ renewables capacity

At the ceremony, Grčić announced a complete overhaul of all 10 units at HPP Đerdap 2, also in cooperation with Siloviye Mashiny, which will add a further 50 MW to EPS’ hydropower capacity, according to the statement.

An agreement with Siloviye Mashiny on the HPP Đerdap 2 revitalization was signed at the beginning of 2019. According to Minister Antić, the plan is to boost the capacity of HPP Đerdap 2, which has not been overhauled since it was built, from 270 MW to 320 MW, and extend its service life by 30 years.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

bulgaria citi Kozloduy financing nuclear power plant

Bulgaria partners with Citi to secure financing for new nuclear power units in Kozloduy

18 July 2025 - The two sides have initiated a partnership for building units 7 and 8 at the existing 2,000 MW Kozloduy nuclear power plant

bih epbih waste incineration tpp tuzla trial

BiH’s power utility EPBiH cancels waste co-incineration trial in Tuzla coal plant

18 July 2025 - Power utility Elektroprivreda Bosne i Hercegovine aborted a waste co-incineration test at its Tuzla coal power plant

Energy Community marks 20th anniversary as integration pillar for Southeastern Europe

Energy Community marks 20th anniversary as integration pillar for Southeastern Europe

17 July 2025 - The Energy Community Ministerial Council held its annual informal meeting in Athens, where the organization was founded twenty years ago

serbia hungary mvm maneks energotehnika juzna backa elektromontaza

Hungary’s MVM becomes majority owner of two Serbian firms

17 July 2025 - MVM is the dominant producer, distributor, and supplier of electricity and gas in Hungary, while the two firms were privately owned