Greece to offer 456 MW in mixed wind and solar capacities in April 15 auction

Photo: Pixabay

Published

April 3, 2019

Country

Comments

comments icon

0

Share

Published:

April 3, 2019

Country:

Comments:

comments icon

0

Share

Greece’s energy regulator, RAE, will offer 456 MW in the country’s first mixed renewable energy auction on April 15, having received eight applications for a total of 637.78 MW in wind and solar capacities.

The applications were submitted by the March 21 deadline, energypress wrote.

A 200 MW solar park project planned by PPC Renewables in Kozani in northern Greece, a 200 MW solar project planned by JUWI Hellas, and two projects with a combined capacity of 104 MW planned by Spes Solaris, a member of the Panagakos group, are among the major projects expected to take part in the mixed renewables auction.

Greece auctioned off around 221.6 MW in combined renewables capacities on December 10, selling approximately 61.94 MW in solar photovoltaic (PV) capacities and 159.65 MW in onshore wind energy capacities, at prices lower than those achieved in the previous auctions, according to an earlier press release from RAE.

The prices achieved in the two successfully completed categories on December 10 were by up to 26.56% below starting prices, RAE said.

With 277.32 MW auctioned off in the first regular competitive auctions, held in July 2018, Greece sold nearly 500 MW in solar and wind capacities in total in 2018.

32% renewables share in gross final energy consumption in 2030 targeted

Greece targets a 32% share of renewables in gross final energy consumption in 2030, from 15.2% in 2016, according to its draft National Energy and Climate Plan (NECP).

Additional targets are for the renewables share in gross final electricity consumption to reach at least 55%, heating and cooling 30% and transport 14% in line with the relevant EU calculation methodology.

Achieving the targets will require the electrification and coupling of final consumption sectors. In particular, a considerable penetration of electric vehicles (EVs) is expected, contributing to various dimensions of the NECP, while for rail transport, full electrification will be achieved much earlier and by 2020 at the latest, according to the draft NECP.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

bih trebinje zhongbo wind farm

Zhongbo Group to install wind farm near Trebinje

03 June 2025 - In September last year, the Government of the Republic of Srpska signed an agreement on strategic cooperation with Zhongbo Group

Wind power investments Turkey surge major plants inaugurated in May

Wind power investments in Turkey surge as major plants inaugurated in May

03 June 2025 - Investments in wind power in Turkey are expected to surpass USD 1.5 billion this year, translating to 1.5 GW of new capacity

BESS factory of 1.5 GWh per year opening near Sofia in Bulgaria

BESS factory of 1.5 GWh per year opening near Sofia in Bulgaria

02 June 2025 - IPS, a Bulgarian manufacturer of battery energy storage systems, is about to launch operations at its new facility near Sofia

Western Balkans urged to step up just transition away from coal

Western Balkans urged to step up just transition measures

02 June 2025 - In its guidelines for the just transition, the Energy Community Secretariat said the Western Balkans lack policies and measures