Renewables

Čibuk 1, Serbia’s largest wind farm, set to start production “earlier than initially planned”

Photo: Masdar

Published

September 10, 2018

Country

Comments

comments icon

0

Share

Published:

September 10, 2018

Country:

Comments:

comments icon

0

Share

Čibuk 1 has reached a number of key milestones and is on schedule to start production in early 2019, according to a press release from the United Arab Emirates’ (UAE) Masdar, the majority stakeholder in Tesla Wind, which owns Vetroelektrane Balkana, the project company behind Čibuk 1, set to become Serbia’s largest wind farm.

GE Renewable Energy, which has supplied the 57 wind turbines for Čibuk 1, tweeted that the 158 MW wind farm is expected to start production “earlier than initially planned.”

Masdar previously said it expected the construction of the 158 MW Čibuk 1 wind farm to be completed in the first half of 2019. The wind farm is set to be funded under the feed-in tariff, reflected on consumers’ electricity bills.

The EUR 300 million investment is backed by some EUR 215 million in lending from the International Finance Corporation (IFC), a member of the World Bank Group, and the European Bank for Reconstruction and Development (EBRD), according to earlier reports.

Čibuk 1 in Dolovo, situated 50 kilometers outside the capital Belgrade, has completed the construction of 33 overhead pylons allowing for the energization of the wind farm’s substation, its connection to existing transmission lines 11 kilometers away, and the handover of the transmission operation building to its operator, Masdar said.

The Čibuk 1 wind farm is expected to provide electricity to 113,000 homes and displace more than 370,000 tonnes of carbon dioxide per year, Masdar said, noting that 52 of the 57 wind turbines have been fully assembled to date.

Vetroelektrane Balkana (WEBG), the project company behind Čibuk 1, is wholly owned by Tesla Wind, a joint venture between Masdar (60%), Finnish energy infrastructure developer Taaleri Energia (30%), and DEG, a subsidiary of Germany’s KfW Group, (10%).

The power purchase agreement (PPA) for Čibuk 1 was signed in October 2016. Serbia has pledged to produce 27% of its domestic power needs from renewable energy sources by 2020, reducing the country’s dependence on coal-fired power generation in line with European Union regulations, Masdar recalled.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Petrol obtains financing EV charging network Slovenia Croatia

Petrol obtains financing for EV charging network in Slovenia, Croatia

15 July 2024 - Slovenia-based Petrol is about to install electric vehicle charging points in 35 locations in its home market and in Croatia.

Green for Growth Fund financial impact targets 2023

Green for Growth Fund tops its financial, impact targets in 2023

15 July 2024 - The Green for Growth Fund kept mitigating climate change and promoting sustainable economic growth last year in its 18 markets

Energy permit not needed for power plants under 1 MW in BiH

15 July 2024 - The Ministry of Energy, Mining and Industry has adopted the rulebook on issuing energy permits and it entered into force on July 6

koncar croatia siemens energy

Končar, Siemens Energy launch new joint venture

15 July 2024 - Croatia’s firm Končar and Siemens Energy have signed a joint venture agreement on the establishment of the Končar - Transformer Tanks