Čibuk 1, Serbia’s largest wind farm, set to start production “earlier than initially planned”

Photo: Masdar

Published

September 10, 2018

Country

Comments

comments icon

0

Share

Published:

September 10, 2018

Country:

Comments:

comments icon

0

Share

Čibuk 1 has reached a number of key milestones and is on schedule to start production in early 2019, according to a press release from the United Arab Emirates’ (UAE) Masdar, the majority stakeholder in Tesla Wind, which owns Vetroelektrane Balkana, the project company behind Čibuk 1, set to become Serbia’s largest wind farm.

GE Renewable Energy, which has supplied the 57 wind turbines for Čibuk 1, tweeted that the 158 MW wind farm is expected to start production “earlier than initially planned.”

Masdar previously said it expected the construction of the 158 MW Čibuk 1 wind farm to be completed in the first half of 2019. The wind farm is set to be funded under the feed-in tariff, reflected on consumers’ electricity bills.

The EUR 300 million investment is backed by some EUR 215 million in lending from the International Finance Corporation (IFC), a member of the World Bank Group, and the European Bank for Reconstruction and Development (EBRD), according to earlier reports.

Čibuk 1 in Dolovo, situated 50 kilometers outside the capital Belgrade, has completed the construction of 33 overhead pylons allowing for the energization of the wind farm’s substation, its connection to existing transmission lines 11 kilometers away, and the handover of the transmission operation building to its operator, Masdar said.

The Čibuk 1 wind farm is expected to provide electricity to 113,000 homes and displace more than 370,000 tonnes of carbon dioxide per year, Masdar said, noting that 52 of the 57 wind turbines have been fully assembled to date.

Vetroelektrane Balkana (WEBG), the project company behind Čibuk 1, is wholly owned by Tesla Wind, a joint venture between Masdar (60%), Finnish energy infrastructure developer Taaleri Energia (30%), and DEG, a subsidiary of Germany’s KfW Group, (10%).

The power purchase agreement (PPA) for Čibuk 1 was signed in October 2016. Serbia has pledged to produce 27% of its domestic power needs from renewable energy sources by 2020, reducing the country’s dependence on coal-fired power generation in line with European Union regulations, Masdar recalled.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Principia CfD backed battery storage facility in Greece

Principia builds CfD-backed battery storage facility in Greece

15 October 2025 - Principia built its first BESS in just six months. The Themelio facility in Chalkidiki in northern Greece has 49 MW in operating power.

CEO Dejan Paravan leaving Slovenian state owned GEN energija report

CEO Dejan Paravan leaving Slovenian state-owned GEN energija – report

15 October 2025 - Dejan Paravan has resigned as Slovenian state-owned GEN energija's CEO and is joining NGEN, according to a news report

Šahmanović: Second submarine cable line with Italy to be installed by 2031

15 October 2025 - Minister of Energy and Mining Admir Šahmanović announced an investment at the EU-Montenegro Investment Conference

montenegro eu investment conference alcazar calderon bijela

Alcazar Energy plans to boost its Montenegro investments to USD 500 million

14 October 2025 - Alcazar Energy intends to increase its investments in Montenegro from USD 200 million to USD 500 million, says Daniel Calderon