UPDATE: Consultancy sought to help award EUR 200 million HPP Dabar project

Photo: ERS

Published

August 22, 2018

Comments

comments icon

0

Share

Published:

August 22, 2018

Comments:

comments icon

0

Share

Hidroelektrana Dabar has launched an international tendering procedure to select a consultancy to provide it with legal, financial, and technical advisory services in the process of awarding a turnkey/engineering, procurement, and construction (EPC) contract for a 160 MW Dabar hydropower plant (HPP Dabar), according to acting general manager Željko Zubac.

Hidroelektrana Dabar, part of hydropower plant operator Hidroelektrane na Trebišnjici (HET), will launch a tendering procedure for the project to complete works on HPP Dabar in early September, Zubac told TrebinjeLive.info.

The consultancy deal is valued at an estimated BAM 2 million (about EUR 1 million) not including VAT or BAM 2.3 million (some EUR 1.17 million) including VAT, Capital has learned. The bid submission deadline is set at October 4.

Zubac recalled that the turnkey project, which would be governed by the public-private partnership (PPP) law, has attracted 19 expressions of interest (EOI), noting that the companies that submitted the EOIs include those from China, the U.S., Spain, Turkey, France, Italy, and the Czech Republic.

The estimated value of the project to build and finance HPP Dabar’s remaining facilities is around EUR 200 million, according to the text of the invitation of EOIs, posted earlier by HET, a subsidiary of Elektroprivreda Republike Srpske (ERS), the power utility of Republika Srpska, the Serb entity of Bosnia and Herzegovina.

Under the preferred financial model, Hidroelektrana Dabar’s future project partner would secure a loan to cover at least 85% of the project cost against a guarantee from the Republika Srpska government. The loan would be repaid in cash or electricity over 15 years, following a 4-year grace period. The interest rate would be at around 3%, according to the text of the invitation.

Hidroelektrana Dabar, which would cover the rest of the project cost from own sources, would own 100% of the 160 MW hydropower plant on the Trebišnjica river. The company has already completed preparatory works for the project, which has so far soaked about BAM 80 million (some EUR 41 million) in investment.

The 160 MW plant, part of a wider Gornji Horizonti hydropower project, would boost HET’s power production by about 50%.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Japan PowerX battery investments EPCG factory Montenegro

Japan-based PowerX eyes battery investments with EPCG, factory in Montenegro

14 May 2026 - PowerX from western Japan signed a deal with Montenegro's state-owned EPCG on planning 500 MWh of battery storage in the Balkan country

EVN Macedonia BESS 10 MW into operation at solar park

EVN Macedonia puts BESS of 10 MW into operation at its solar park

13 May 2026 - EVN Macedonia commissioned a battery energy storage system within its Probištip photovoltaic plant in North Macedonia

Energy companies confront dual mandate keeping supply secure while accelerating green transition BEF 2026

Energy companies in Western Balkans confront dual mandate – keeping supply secure while accelerating green transition

13 May 2026 - Companies in the region have challenges in energy security, decarbonization and digitalization, and the key is investing in production, the grid and batteries, according to the panel on power system transition at Belgrade Energy Forum 2026

serbia eu region bef 2026 ivan asanovic cges market coupling

Asanović: Montenegro expects European Commission to clear market coupling by end-June

12 May 2026 - Ivan Asanović, CEO of Montenegro's transmission system operator, participated in the panel on transmission grid development at BEF 2026