The delayed EUR 3.6 million project to build a biomass heating plant in Novi Pazar as part of a wider plan for 10 district heating operators in Serbia to switch from fossil fuels to renewable energy sources is now expected to be completed in 2019, according to assistant mayor Faruk Suljević.

Suljević told Sto Plus, a local radio broadcaster, that he believes the local government will reach an agreement within a month to buy around 1.5 hectares of land belonging to bankrupt textile firm Raška, where the biomass heating plant is planned to be built.

“We will simultaneously work on producing a preliminary design plan and other documentation in order to obtain a construction permit by the end of the year. After that, we expect the Ministry of Mining and Energy and the Public Investment Management Office to launch a tendering procedure and select the contractor, which could start construction works in the spring of next year. The works should last five or six months,” Suljević said.

A study has shown that the biomass-fired plant could provide heating to some 170,000 new users in Novi Pazar, given that a large number of public institutions in the center of the town, newly-built residential properties, and industrial facilities are not yet connected to the district heating network, Suljević said, noting that all these potential new users will be offered an economically acceptable price of heating that will make it unnecessary for them to procure own heating boilers.

The wider project to build 10 biomass heating plants in Serbia is worth EUR 27 million, EUR 20 million of which is financed with a EUR 20 million loan from German development bank KfW, which is also providing a EUR 2 million grant, and a EUR 5 million grant from the government of Switzerland.

The municipalities in question include Mali Zvornik, Nova Varoš, Prijepolje, Bajina Bašta, ValjevoPriboj, Kladovo, and Majdanpek.

KfW has offered the 2nd tranche of credit for an additional 15-20 district heating operators in Serbia to convert from fossil fuel to biomass. The Development of a Sustainable Bioenergy Market in Serbia program is implemented jointly by the German development organization GIZ and KfW.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Green for Growth Fund financial impact targets 2023

Green for Growth Fund tops its financial, impact targets in 2023

15 July 2024 - The Green for Growth Fund kept mitigating climate change and promoting sustainable economic growth last year in its 18 markets

IRENA La Camera renewables must grow higher speed scale

IRENA’s La Camera: Renewables must grow at higher speed, scale

12 July 2024 - IRENA's Director-General Francesco La Camera warned of ongoing patterns of concentration in geography in renewables deployment as well as against complacency

green steel electric vehicles study transport environment

Switching to green steel would add just EUR 8 per electric vehicle by 2040

11 July 2024 - Switching to 40% green steel would add just EUR 57 to the sticker price of an electric vehicle in 2030, according to an analysis by T&E

Albania declares eight winners at 300 MW solar power auction

Albania declares eight winners at 300 MW solar power auction

10 July 2024 - The lowest bid at Albania's solar power auction came in at EUR 39.7 per MWh, against a starting level of EUR 59.97 per MWh