Bulgaria’s NEK reports net loss in H1, to cancel some projects

Photo: NEK

Published

August 6, 2018

Country

Comments

comments icon

0

Share

Published:

August 6, 2018

Country:

Comments:

comments icon

0

Share

Power utility Natsionalna Elektricheska Kompania (NEK) reported a BGN 74 million (EUR 37.8 million) net loss for the first six months of the year, according to the interim financial report published on the website of the Ministry of Finance, the Bulgarian media reported. The company said that due to poor financial results some investments will be canceled.

In the same period last year, NEK had a BGN 954,000 (EUR 487,000) loss, Publicis.bg reported.

Because of the poor financial condition NEK does not plan to continue financing several investments, including the Upper Arda cascade, the Mesta cascade, and several smaller projects, in the next five years, Bulgarian news agency BTA reported.

In the first half of this year, NEK reported an operating loss of BGN 55 million (EUR 28.1 million) and positive cash flow from operating activities of BGN 74.4 million (EUR 38.8 million). The uncovered loss from previous periods amounted to BGN 1.19 billion (EUR 608.4 million).

NEK’s liabilities to the owner, the Bulgarian Energy Holding (BEH), reached BGN 540.3 million (EUR 276 million), including overdue liabilities of almost BGN 361 million (EUR 184.5 million).

The activity of the company is highly dependent on the support of BEH, as well as other sources of financing, according to the report.

The management is confident that with the financial support of BEH, NEK will be able to continue its activities and repay its obligations without selling assets and without making any major revisions to its operations.

The report also brings details on the Belene nuclear power plant (NPP) project. Until June 30, 2018 the cost of the project including assets under construction reached BGN 2.18 billion (EUR 1.09 billion).

The management sees considerable uncertainty about the future realization of the project and the recoverable value of the assets related to the Belene NPP, the website noted.

NEK operates with 30 HPPs and pumped-storage plants, with a total installed capacity of 2,713 MW in the generating mode, and 937 MW in the pumping mode.

The 14 largest HPPs have a total installed capacity of 2,480 MW.

Tags: , ,
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Serbia drafts just transition action plan public debate

Serbia drafts just transition action plan

30 May 2025 - The Ministry of Mining and Energy has published a draft just transition action plan and launched a public debate

Regional Power Sector Exchange Western Balkans disitribution system operator dso grids ohrid giz

Third Regional Power Sector Exchange in Ohrid: Power grids at core of energy transition

30 May 2025 - The third Regional Power Sector Exchange of the Western Balkans gathered over 80 energy professionals from the Western Balkans

two solar power plants egesa enerji vojvodina

Turkey’s Egesa Enerji to build two solar power plants in Serbia’s Vojvodina province

30 May 2025 - Turkish company Egesa Enerji has launched a project to build two solar power plants in Vojvodina, with a total nominal capacity of 8.6 MW

Green for Growth Fund partnership Swedish International Development Cooperation Agency Sida

Green for Growth Fund launches partnership with Swedish International Development Cooperation Agency

30 May 2025 - GGF and the Swedish International Development Cooperation Agency are expanding green lending in the Western Balkans and the EU's Eastern Neighborhood