Delivery of turbines for Malibunar wind farm in Serbia started

Photo: Elicio

Published

August 8, 2017

Country

Comments

0

Share

Published:

August 8, 2017

Country:

Comments:

0

Share

Delivery of wind turbine parts for the Malibunar wind farm has begun, the Belgian company Elicio NV, which builds two wind farms in northern Serbia, announced.

The delivery of turbine parts from the Port of Pančevo on the Danube river to the location of the wind park in northern Serbia started on August 8. It will continue during the week until Friday, Elicio said.

The company earlier closed the deal with German producer Senvion for the delivery of four MM100 turbines with a total capacity of 8 MW for Malibunar wind farm.

Malibunar wind park is expected to become operational by the end of the year. Expected annual production is 23.8476 MWh and the investment’s value is EUR 13,8 million.

Senvion and Elicio also signed a contract for the delivery, installation and commissioning of 21 MM100 turbines for 42 MW Alibunar wind farm. Alibunar is located near Malibunar and, according to plan, the wind park should be installed there in the first half of 2018.

Senvion will take care of servicing over a period of 15 years for both projects.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

DJokic-new-energy-capacities-2030

Đokić: Republic of Srpska to build 1.200 MW of new energy facilities by 2030

13 May 2024 - The Republic of Srpska plans to build 1,200 MW of new energy facilities by 2030, said Energy and Mining Minister Petar Đokić, adding that the Bileća solar power plant has been completed

CBAM ante portas – the ball is in Serbia’s court to facilitate conditions for its companies

CBAM ante portas – the ball is in Serbia’s court to facilitate conditions for its companies

12 May 2024 - Industrial players in Serbia have all the knowhow for minimizing emissions and participating in the country's environmental renewal, according to Lafarge Serbia's CEO Dimitrije Knjeginjić

State owned DEM operate Slovenia fourth wind turbine

State-owned DEM to operate Slovenia’s fourth wind turbine

10 May 2024 - Dravske elektrarne Maribor hired Ljubljana-based Hmezad TMT for the construction of a single-turbine wind power plant in southern Slovenia

eu solar rooftop standard directive epbd

EU Solar Rooftop Standard could initiate installation of 150 GW to 200 GW of rooftop PV

09 May 2024 - The standard is part of the EU Energy Performance of Buildings Directive, which entered into force yesterday