Renewables

Small hydropower plants project stuck with deadline nigh

Published

May 6, 2015

Country

Comments

comments icon

0

Share

Published:

May 6, 2015

Country:

Comments:

comments icon

0

Share

Zorana Mihajlović, Serbian vice premier and minister for construction and infrastructure, said the development of small hydropower facilities (SHPPs) for which investors have been given the locations, has stopped, B92.net reported.

She noted that while she was the minister responsible for energy, in the previous mandate, two public invitations were published for the locations. Altogether, there were 450 locations on offer, with memorandums subsequently signed for 293 lots.

The deadline for launching 200 small hydro plants expires in June without a single one built, Center for Investigative Journalism (CINS) said in a report. Investors are suffering losses and many are giving up on their endeavour, accusing the state of being inefficient. Others still struggle to get permits and hope for help from the Ministry of Mining and Energy.

Apart from the procedure, there was no help to solve ownership issues and power monopoly Elektroprivreda Srbije (EPS) isn’t making grid connection any simpler, investors say.

Some of them added the ministry doesn’t even communicate with them. After a year in the process, in September last year it cancelled a third of the location permits, ones that belonged to investors who hadn’t submitted investment projects, but it didn’t inform them.

A review by Serbia’s public water management enterprise Srbijavode led to the conclusion that at least one-fifth of locations the government offered to investors to build mini hydroelectric facilities was on dry land, Serbian daily Večernje novosti said in April.

Out of 600, only around 60 places are suitable to build a dam on a small stream, while the rest is in national parks or owned by citizens who do not wish to sell property or ask up to EUR 10,000 for the location.

Related Articles

Green for Growth Fund financial impact targets 2023

Green for Growth Fund tops its financial, impact targets in 2023

15 July 2024 - The Green for Growth Fund kept mitigating climate change and promoting sustainable economic growth last year in its 18 markets

IRENA La Camera renewables must grow higher speed scale

IRENA’s La Camera: Renewables must grow at higher speed, scale

12 July 2024 - IRENA's Director-General Francesco La Camera warned of ongoing patterns of concentration in geography in renewables deployment as well as against complacency

green steel electric vehicles study transport environment

Switching to green steel would add just EUR 8 per electric vehicle by 2040

11 July 2024 - Switching to 40% green steel would add just EUR 57 to the sticker price of an electric vehicle in 2030, according to an analysis by T&E

Albania declares eight winners at 300 MW solar power auction

Albania declares eight winners at 300 MW solar power auction

10 July 2024 - The lowest bid at Albania's solar power auction came in at EUR 39.7 per MWh, against a starting level of EUR 59.97 per MWh