Turkey aims to almost double electricity generation capacity by 2035

national energy plan Turkey aims double electricity generation capacity 2035

Photo: iStock

Published

January 6, 2023

Country

Comments

comments icon

0

Share

Published:

January 6, 2023

Country:

Comments:

comments icon

0

Share

Turkey’s National Energy Plan for 2035 revealed the ambition to boost solar power capacity by five times and triple the total size of wind power plants. The country intends to increase total electricity generation capacity to 189.7 GW, mostly with renewables. Last year it surpassed the 100 GW threshold.

Turkey published its National Energy Plan for the period until 2035, laying out steps toward reaching the target of net zero greenhouse gas emissions by 2053. The combined capacity of power plants in the country is seen at 189.7 GW. In comparison, the level topped 100 GW early last year. Renewables account for 74.3% of the planned additions.

Green electricity’s share in capacity is projected at 64.7%. Statistics show they accounted for 54% one year ago. The target shows would continue to significantly rely on fossil fuels. Turkey counts on its vast newly discovered offshore gas reserves. Its coal power plant pipeline is one of the biggest in the world.

Nevertheless, expansion in the solar and wind power sectors remains impressive and the country is determined to spur investments in equipment.

Turkey’s goal for solar power for 2035 is 59.9 GW compared to approximately 9 GW of total photovoltaic capacity that it currently hosts.

In 2035, wind power plants should have a combined 29.6 GW, the document reads, of which 5 GW would be offshore. It implies almost tripling the capacity as in 2022 the gauge topped 11 GW. The goal for solar power is 59.9 GW. Turkey currently hosts approximately 9 GW of photovoltaic capacity.

Hydropower plants now have the largest share. They are planned to grow to 35.1 GW in total by 2035, compared to 31.5 GW as of last March. The first segment of Turkey’s first nuclear power plant Akkuyu is scheduled to be commissioned this year. The National Energy Plan aims at a total nuclear energy capacity of 7.2 GW at the end of the period.

Annual electricity consumption is expected to grow 3.5% per year until 2035 to hit 510.5 TWh.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

montenegro epcg edf hpp krusevo sahmanovic dragas mrvaljevic

Montenegro, EDF discuss Kruševo pumped storage hydropower project

06 April 2026 - Representatives of the Ministry of Energy and Mining and state-owned power utility Elektroprivreda Crne Gore held talks with EDF's delegation

power grid capacity renewables demand eu ember

Ember: Lack of grid capacity threatens EU’s energy security

06 April 2026 - The European Union's grids lack the capacity to connect new renewables and meet additional electricity demand

PPC Group 2 13 GW photovoltaics including EU second largest solar park

PPC Group completes 2.1 GW of photovoltaics including EU’s second-largest solar park

06 April 2026 - Public Power Corp. said its new PV cluster is the biggest in Europe. It includes Phoebe, the second-largest solar park in the European Union.

montenegro memorandum mou bgen bef sahmanovic branislava jovicic

Montenegro’s Ministry of Energy seals strategic partnership with Balkan Green Energy News

03 April 2026 - The Ministry of Energy and Mining of Montenegro and Balkan Green Energy News signed a memorandum of understanding