Three bids for strategic partner for 1 GW of solar in Serbia

Three bids for strategic partner for 1 GW of solar in Serbia

Photo: Oleksandr Ryzhkov on Freepik

Published

September 21, 2023

Country

Comments

comments icon

0

Share

Published:

September 21, 2023

Country:

Comments:

comments icon

0

Share

The Government of Serbia has received three bids for a strategic partnership to install solar power plants totaling 1 GW, with batteries, Balkan Green Energy News learned.

In late July, the Ministry of Mining and Energy of Serbia launched a public call to select a strategic partner to install solar power plants totaling 1 GW in connection capacity (1.2 GW in peak terms) alongside at least 200 MW of battery storage, with the possibility of storing a minimum of 400 MWh.

The deadline for submitting offers expired yesterday, when the bids were opened.

The offers were submitted by China Energy International Group Co. Ltd., Direkt Solar Kühn GmbH, and a consortium consisting of Hyundai Engineering Co. Ltd., Hyundai Engineering America Inc. and UGT Renewables LLC.

Direkt Solar Kühn’s bid did not meet the criteria determined in the public call.

The strategic partner should build the facilities and hand them over to government-controlled power utility Elektroprivreda Srbije (EPS) under a turnkey deal.

Of note, the Government of Serbia also intends to look for a strategic partner for the construction of wind farms with a total capacity of 1 GW.

The working group is tasked with selecting the best bid

The procedure for selecting the strategic partner is led by a working group. After determining whether the companies met the criteria for participation, it is tasked with evaluating the bids. Ones that do not meet the criteria will not be considered, the public call reads.

Eligible companies had to demonstrate experience in the construction of power plants, with an overall capacity of at least 25,000 MW in their track record. They must have more than 5,000 employees, and a EUR 4.5 billion turnover each year over the last three years.

After ranking the bids, the working group needs to propose a decision with regard to the selection of the strategic partner and submit a report to the government.

The procedure is conducted under different rules than for public procurement and public-private partnerships

The public call was launched under a framework different than the ones for public procurement and public-private partnership.

After the government adopts a decision, the working group conducts negotiations with the selected partner with the aim of signing a project implementation contract, the document reads. In the same phase, a project financing agreement needs to be drafted.

The working group then submits a report to the government with a proposal to sign the contract or to determine other next steps, depending on the result of the negotiations.

Finally, the government and the selected strategic partner sign the project implementation contract. It comes into force after the project financing contract is signed and takes effect.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Enery inaugurates region largest battery system Nova Zagora in Bulgaria

Enery inaugurates region’s largest battery system in Nova Zagora in Bulgaria

07 May 2026 - Austria-based Enery has commissioned the Nova Zagora BESS. It is the largest battery system in Central and Eastern Europe, the company said.

Rezolv Energy 225 MW solar park St. George in Bulgaria

Rezolv Energy commissions 225 MW solar park St. George in Bulgaria

07 May 2026 - One of Bulgaria’s largest solar parks is now fully operational. Rezolv Energy built the St. George facility on the site of the former Silistra airport.

epcg projects milutin đukanovic

Montenegrin utility EPCG developing 639 MW of power generation and storage projects

06 May 2026 - EPCG is developing solar, wind, battery, and hydropower projects totaling 639 MW, with an expected annual output of over 1 TWh, wrote Milutin Đukanović, President of the Board of Directors

montenegro tso cges loan afd rte substations

Montenegro’s TSO eyes EUR 25 million loan to upgrade two substations

06 May 2026 - The Government of Montenegro is providing a guarantee for a loan agreement with France's AFD