Serbia has completed the feasibility study for pumped storage hydropower plant Bistrica and the cost is estimated at more than EUR 1 billion, Minister of Mining and Energy Dubravka Đedović said after speaking to Ambassador of Japan Akira Imamura about joint energy and environmental projects.

Dubravka Đedović Handanović pointed out that in the next three to four years, until the beginning of the Specialized Expo 2027 exhibition in Belgrade, the government would invest more than ever before in energy. Serbia will complete a lot of projects including a gas interconnection with North Macedonia, the Serbia-Hungary oil pipeline, Kostolac wind farm, and investments in the transmission and distribution grids, she added.

Đedović Handanović said work is underway on technical documentation for important projects, such as Bistrica and another pumped storage hydroelectric plant – Đerdap 3. She argued they would secure a more stable electricity supply and improve the balancing of the power system.

Đedović Handanović: Numerous Japanese companies are interested in the Bistrica project

Bistrica, in her view, will be a key electricity supply facility for Serbia to integrate new clean energy capacities and improve the balancing of intermittent energy sources.

This year is very important for the completion of technical documentation for the Bistrica project, Đedović Handanović underscored. The feasibility study was completed, and the total investment is estimated at more than EUR 1 billion she explained.

According to the minister, Japan International Cooperation Agency (JICA) is interested in financing, while numerous companies from Japan are willing to take part in the project’s implementation.

Imamura: Energy storage technology is very developed in Japan

Ambassador Akira Imamura expressed satisfaction that there is interest from both sides in cooperation in the construction and financing of Bistrica, but also in other energy projects. He stressed that the energy storage technology is highly developed in Japan.

Japanese companies are ready to share knowledge and experience with Serbian energy companies in building renewables, balancing and storage facilities, which is nowadays of great importance for energy systems, Imamura asserted.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

croatia hep koncar hpp varazdin contract

Croatia’s HEP to invest EUR 157 million in HPP Varaždin

19 January 2026 - HEP and Končar have signed a contract for the reconstruction of the generating units at the Varaždin hydropower plant

IRENA Global daily flexibility needs are quadrupling by 2050

IRENA: Global daily flexibility needs are quadrupling by 2050

19 January 2026 - IRENA expects the world's electricity system flexibility needs, on a daily timescale, to quadruple by 2050 from the 2019 level

Bulgaria host renewable electricity plants on Luxembourg s behalf

Bulgaria to host renewable electricity plants on Luxembourg’s behalf

16 January 2026 - Bulgaria joined Finland as a host country for renewables projects funded by Luxembourg, under the RENEWFM program for 2026

Renewables account 99 Turkey net electricity capacity additions

Renewables account for 99% of Turkey’s net electricity capacity additions

16 January 2026 - Electricity capacity in Turkey reached 122 GW in 2025, of which 62% was from renewables, according to the SHURA Energy Transition Center