Electricity

Macedonian day-ahead market launch scheduled for the end of November 2019

Photo: Pixabay

Published

November 23, 2018

Country

Comments

comments icon

0

Share

Published:

November 23, 2018

Country:

Comments:

comments icon

0

Share

The launch of the former Yugoslav Republic of Macedonia’s day-ahead market (DAM) is scheduled for the end of November 2019, while the go-live of Bulgaria and Macedonia (BG-MK) market coupling will follow in January 2020, the Energy Community Secretariat said in its latest Western Balkans 6 (WB6) Electricity Monitoring Report.

WB6 parties failed to finalize activities in line with the deadlines and commitments, such as unbundling of system operators, independence of the national regulatory authorities and the implementation of the Trans-European Network Regulation, the Secretariat said in a press release.

In addition, the regulation of supply prices for households and small customers was prolonged in a majority of the WB6 parties. According to the Secretariat, this trend is detrimental to the development of competition in the market, because regulated prices are under the market level.

Spot Market Development: roadmap for Bulgaria-Macedonia market coupling in November 2018

In the reporting period, compared to the last report published in June, the only tangible progress was made in FYROM, where the electricity market operator (MEMO) was spun out of the transmission system operator in line with the Energy Law, the report reads.

A detailed roadmap for the Bulgaria-Macedonia market coupling was adopted and a non-disclosure agreement is expected to be signed by the end of November 2018, the report concludes, adding that the map also defines the launch of the Macedonian DAM and the go-live of the Bulgaria-Macedonia market coupling.

Activities on setting up companies responsible for the operation of the day-ahead markets have been delayed in Albania and Montenegro. A decision on the establishment and ownership structure of the operator of the Albanian power exchange (APEX) is expected to be finalized in November 2018, as well as a request for offers for strategic partnership by the Montenegrin BELEN.

Regional Capacity Allocation: agreement between KOSTT, ENTSO-E moves forward

Progress towards the entry into force of the Connection Agreement between KOSTT and ENTSO-E was noted in the reporting period. Elektrosever, a subsidiary of Serbia’s power utility Elektroprivreda Srbije (EPS), was registered as the power supply company in the Kosovo Business Registration Agency in November 2018. Licensing of this company is a precondition for the entry into force of the Connection Agreement.

Albania signed an agreement with the Security Coordination Center, which is now providing services to the transmission system operators from all WB6, with the exception of Kosovo*, which has not yet decided on using the services of any of the existing regional security coordinators.

Cross-cutting measures: regulation of household prices prolonged

The reporting period was marked by delay in the regulation of supply prices for households and small customers in most of the WB6 parties, the report finds.

In addition to the already postponed price deregulation for medium voltage customers by April 2019, the regulator of Kosovo* postponed the deregulation of prices for 10 kV by April 2020 by its decision of October 2018.

A tender for the supplier of last resort was not yet published in Montenegro, while in Serbia, the regulator proposed continuing regulation of prices for guaranteed supply in its September 2018 report on the need for further regulation of these prices.

Furthermore, a right of all customers to change their supplier is still withheld in Albania and Macedonia, where it is expected to be phased out as of 2019.

Cross-border balancing: Macedonia prepares new balancing rules

According to the report, Macedonia, which is the only WB6 party where regulated companies are effectively still exempted from balance responsibility, is finalizing the process of adoption of new balancing rules.

Except in Bosnia and Herzegovina, where 4 big production companies are competing in the balancing market, the provision of balancing services is essentially limited to one single balancing service provider, namely the incumbent producer.

This was used as a justification for the Serbian regulator to propose continuing with the regulation of balancing reserve prices in its new report, justifying the need for further regulation of these prices.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

croatia geothermal energy soyak power plant legrad 1

Soyak to install 80 MW geothermal power plant in Croatia

25 December 2024 - Croatia has only one geothermal power plant - the 16.5 MW Velika 1 in Ciglena near Bjelovar

Energy Community pace of integration implementation EU steady but CBAM looms

Energy Community’s EU integration pace steady but CBAM looms

25 December 2024 - Energy Community contracting parties showed a tendency this year toward steady transposition and implementation of European law

Romania calls agricultural food firms apply solar wind power grants

Romania calls agricultural, food firms to apply for solar, wind power grants

25 December 2024 - The Agency for Financing Rural Investments (AFIR) has EUR 150 million in grants for photovoltaic and wind power in Romania

republic of srpska gacko ugljevik coal power

Republic of Srpska doesn’t have EUR 357 million to maintain production in coal power plants

24 December 2024 - Minister Petar Đokić held a meeting with the boards of directors and supervisory boards of coal complexes Gacko and Ugljevik