Renewables

Investors submit bank guarantees for 4 GW of new power plants in Serbia

serbia grid connection bank guarantees ems

Photo: Reginal from Pixabay

Published

July 4, 2024

Country

Comments

comments icon

0

Share

Published:

July 4, 2024

Country:

Comments:

comments icon

0

Share

Bank guarantees for solar, wind and hydropower projects and substations, within the transmission system in Serbia, were provided for 28 facilities with an overall capacity of 4,000 MW. Developers of 51 investments in total, divided into two groups, had a deadline to submit them by June 24 or July 1.

Obligatory bank guarantees of EUR 25,000 per MW of capacity are from a regulation introduced in October 2023. The intention was to unclog the grid connection approval process which, according to investors, has been hold for about two years. It is one of the main steps for solar park and wind farm projects.

After the adoption of the Law on the Use of Renewable Energy Sources in 2021, Serbia’s transmission system operator (TSO) Elektromreža Srbije (EMS) received requests to connect almost 20 GW of new power plants. It was much more than the network could integrate – a combined 5,800 MW in capacity as of September of last year.

EMS told Balkan Green Energy News that by July 1, it received guarantees for 28 facilities with a total capacity of 4,000 MW, not including projects being reviewed in line with the law.

The company said it would publish the list on its website by the end of the week. Balkan Green Energy News learned there is only one substation on the list and that the rest are all power plants.

After providing bank guarantees, investors have two months to sign a connection agreement with EMS

Of note, 51 facilities met the conditions for the conclusion of the agreement on the preparation of the connection study, defined in the directive on the conditions of electricity delivery and supply. In total, there were 24 solar projects of an overall 3,278.5 MW, 18 wind power plants with a combined 3,239.4 MW, and one hybrid power plant of 150 MW in capacity.

Pumped-storage hydropower project Bistrica, with a proposed capacity of 656 MW, was also on the wider list together with four other hydropower plants and three substations.

The condition for starting the procedure for concluding the agreement on the connection of the facility to the transmission system is the submission of a bank guarantee within 60 days from the submission of the connection study.

“In line with the regulation on the conditions of delivery and supply of electricity, if the bank guarantee is not submitted within two months from the delivery of the connection study, the study ceases to be valid and it is considered that the applicant has abandoned the connection process,” EMS said.

After bank guarantees are provided, investors have two months to sign the connection agreement with Serbia’s TSO.

New opportunity from September 1

If an investor doesn’t sign the connection agreement within the deadline, the connection study is annulled so they have to replace it.

Investors will have the opportunity for that in the next interval, which begins on September 1, EMS explained. By August 1 they have to submit a complete application for signing the contract on the development of the connection study, the TSO added.

By submitting a bank guarantee, the investor accepts the obligation to meet the deadlines throughout the project. Otherwise, the new regulation defines the situations in which EMS can collect the guarantee.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

ACER Zinglersen Integrate electricity markets flexibility new era already here BEF 2025

ACER’s Zinglersen: Integrate electricity markets to bolster flexibility as new era is already here

28 May 2025 - The number of hours with negative power prices reached an all-time high for two years in a row, which means a new era is here, ACER's Director Christian Zinglersen said at BEF 2025

NGEN BEF 2025 decentralized electricity grid Roman Bernard BEF 2025

NGEN showcases solutions at BEF 2025 for decentralized electricity grid of tomorrow

28 May 2025 - Slovenia-based NGEN is expanding throughout Europe with its software platforms and equipment and BESS for decentralized grids

belgrade energy forum bef 2025 flexibility services batteries koer ngen ems alteo cybergrid

BEF 2025: Digitalization, open markets, time are major preconditions for flexibility services mainstreaming

27 May 2025 - The panel called Market Flexibility: The Backbone of a Resilient Energy System was one of the eight sessions at Belgrade Energy Forum 2025

Fortis Energy Gavrilovic developing huge portfolio in SEE

Velimir Gavrilović, Fortis Energy: We are developing huge portfolio in SEE

27 May 2025 - Fortis Energy is working on renewable energy projects of 2 GW altogether in Southeast Europe, of which half is in Serbia