Greece to install 1 GW undersea interconnection with Dodecanese islands

IPTO launches tender for first stage of Dodecanese islands interconnection

Photo: IPTO

Published

November 18, 2024

Country

Comments

comments icon

0

Share

Published:

November 18, 2024

Country:

Comments:

comments icon

0

Share

Greece is set to get its second high-voltage direct current (HVDC) power interconnection by the end of 2027, as Independent Power Transmission Operator (IPTO or, in Greek, Admie) launched a tender for the installation of an underwater line between Corinth and the remote island of Kos.

The tender, a part of the plan for the interconnection of the Dodecanese islands to the mainland, includes two parallel cables of 500 MW each as well as two conversion stations, one on both ends. The length is 380 kilometers.

The budget is EUR 630 million for the lines and another EUR 789.1 million for the converters. Concessionaires will have 36 months to carry out the works.

Manousakis: Paving the way to utilize the full renewable potential of islands

After the line is completed, further works would be carried out to connect the nearby islands of Karpathos, Rhodes, Symi, Kalymnos, Patmos and Arkia.

The ultimate goal is to reduce carbon emissions and ensure the islands’ stable supply, which currently depends on costly diesel units. At the same time, they will be able to accommodate more renewable energy plants within their grid, alongside energy storage.

The Corinth-Kos connection will unite the Dodecanese islands with the mainland high-voltage system for the first time, paving the way for the full utilization of the onshore and offshore renewables potential of dozens of islands, said the transmission system operator’s Chairman and CEO Manos Manousakis.

All large islands to be connected by 2030

IPTO claims that by 2030 all large islands in the Aegean would be connected to the mainland, leading to a EUR 3.6 billion cost drop for electricity consumers in the period 2029-2053. Apart from the Dodecanese, the islands of the northern Aegean are also included under a different interconnection project.

It should be noted that IPTO is completing the HVDC interconnection between Attica and Crete, the country’s biggest island. It also participates in a project to connect Crete to Cyprus and Israel, the so-called Great Sea Interconnector.

The TSO aims to upgrade all existing links to neighboring countries as well as to build one through the Adriatic Sea, to Slovenia, and then Germany. The project is called Green Aegean.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Battery storage investors Romania rapidly expanding project pipeline

Battery storage investors in Romania rapidly expanding project pipeline

16 August 2025 - In an rising investment wave, firms in Romania are combining energy storage with solar, wind and hydropower or building standalone systems

north macedonia guarantees of origin solar power plant oslomej

Good start for North Macedonia: in first two months 100k+ guarantees of origin issued

15 August 2025 - In April, the National Electricity Market Operator (MEMO) established the Register of Guarantees of Origin for electricity

serbia eps profit results 2025

Serbia’s EPS reports EUR 234 million profit for first half of 2025

15 August 2025 - State-owned Elektroprivreda Srbije (EPS) achieved lower profit in the first half of the year than in the same period of 2024

North Macedonia draft law envisages renewable energy auctions for CfDs

North Macedonia’s draft law envisages renewable energy auctions for CfDs

14 August 2025 - North Macedonia's draft Law on the Use of Energy from Renewable Sources covers auctions, CfDs, prosumers and renewable energy communities