Greece to install 1 GW undersea interconnection with Dodecanese islands

IPTO launches tender for first stage of Dodecanese islands interconnection

Photo: IPTO

Published

November 18, 2024

Country

Comments

comments icon

0

Share

Published:

November 18, 2024

Country:

Comments:

comments icon

0

Share

Greece is set to get its second high-voltage direct current (HVDC) power interconnection by the end of 2027, as Independent Power Transmission Operator (IPTO or, in Greek, Admie) launched a tender for the installation of an underwater line between Corinth and the remote island of Kos.

The tender, a part of the plan for the interconnection of the Dodecanese islands to the mainland, includes two parallel cables of 500 MW each as well as two conversion stations, one on both ends. The length is 380 kilometers.

The budget is EUR 630 million for the lines and another EUR 789.1 million for the converters. Concessionaires will have 36 months to carry out the works.

Manousakis: Paving the way to utilize the full renewable potential of islands

After the line is completed, further works would be carried out to connect the nearby islands of Karpathos, Rhodes, Symi, Kalymnos, Patmos and Arkia.

The ultimate goal is to reduce carbon emissions and ensure the islands’ stable supply, which currently depends on costly diesel units. At the same time, they will be able to accommodate more renewable energy plants within their grid, alongside energy storage.

The Corinth-Kos connection will unite the Dodecanese islands with the mainland high-voltage system for the first time, paving the way for the full utilization of the onshore and offshore renewables potential of dozens of islands, said the transmission system operator’s Chairman and CEO Manos Manousakis.

All large islands to be connected by 2030

IPTO claims that by 2030 all large islands in the Aegean would be connected to the mainland, leading to a EUR 3.6 billion cost drop for electricity consumers in the period 2029-2053. Apart from the Dodecanese, the islands of the northern Aegean are also included under a different interconnection project.

It should be noted that IPTO is completing the HVDC interconnection between Attica and Crete, the country’s biggest island. It also participates in a project to connect Crete to Cyprus and Israel, the so-called Great Sea Interconnector.

The TSO aims to upgrade all existing links to neighboring countries as well as to build one through the Adriatic Sea, to Slovenia, and then Germany. The project is called Green Aegean.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Renewable energy project frenzy in Greece defies curtailments, grid constraints

Renewable energy project frenzy in Greece defies curtailments

20 December 2024 - Applications for new renewable energy projects continued unabated in Greece in 2024 according to Independent Power Transmission Operator

north macedonia esm kfw bogdanci bitola solar wind uncev Moritz Remé

North Macedonia’s ESM secures loan, grant for solar projects, wind farm Bogdanci

20 December 2024 - The solar power plants will be installed within coal mining and energy complexes REK Bitola and REK Oslomej

Electricity sector officials visit Albania trailblazing photovoltaic plants GIZ regional decarbonization project

Electricity sector officials visit Albania’s trailblazing photovoltaic plants as part of GIZ regional decarbonization project

20 December 2024 - GIZ organized a field trip and presentations in Albania for energy ministries, electricity DSOs and regulators in the Western Balkans

hydropower plants bistrica agreement viskovic djokic

Financing secured for three hydropower plants on Bistrica river

19 December 2024 - The Republic of Srpska has signed an agreement with Chinese company AVIC to finance three hydropower plants on the Bistrica river