Greece to install 1 GW undersea interconnection with Dodecanese islands

IPTO launches tender for first stage of Dodecanese islands interconnection

Photo: IPTO

Published

November 18, 2024

Country

Comments

comments icon

0

Share

Published:

November 18, 2024

Country:

Comments:

comments icon

0

Share

Greece is set to get its second high-voltage direct current (HVDC) power interconnection by the end of 2027, as Independent Power Transmission Operator (IPTO or, in Greek, Admie) launched a tender for the installation of an underwater line between Corinth and the remote island of Kos.

The tender, a part of the plan for the interconnection of the Dodecanese islands to the mainland, includes two parallel cables of 500 MW each as well as two conversion stations, one on both ends. The length is 380 kilometers.

The budget is EUR 630 million for the lines and another EUR 789.1 million for the converters. Concessionaires will have 36 months to carry out the works.

Manousakis: Paving the way to utilize the full renewable potential of islands

After the line is completed, further works would be carried out to connect the nearby islands of Karpathos, Rhodes, Symi, Kalymnos, Patmos and Arkia.

The ultimate goal is to reduce carbon emissions and ensure the islands’ stable supply, which currently depends on costly diesel units. At the same time, they will be able to accommodate more renewable energy plants within their grid, alongside energy storage.

The Corinth-Kos connection will unite the Dodecanese islands with the mainland high-voltage system for the first time, paving the way for the full utilization of the onshore and offshore renewables potential of dozens of islands, said the transmission system operator’s Chairman and CEO Manos Manousakis.

All large islands to be connected by 2030

IPTO claims that by 2030 all large islands in the Aegean would be connected to the mainland, leading to a EUR 3.6 billion cost drop for electricity consumers in the period 2029-2053. Apart from the Dodecanese, the islands of the northern Aegean are also included under a different interconnection project.

It should be noted that IPTO is completing the HVDC interconnection between Attica and Crete, the country’s biggest island. It also participates in a project to connect Crete to Cyprus and Israel, the so-called Great Sea Interconnector.

The TSO aims to upgrade all existing links to neighboring countries as well as to build one through the Adriatic Sea, to Slovenia, and then Germany. The project is called Green Aegean.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Two PV parks of 117 MW in total coming online near Bucharest

Two PV parks of 117 MW in total coming online near Bucharest

23 April 2025 - Eximprod is commissioning a 65 MW solar park north of Bucharest and Simtel arranged loans for the completion of a 52 MW plant in Giurgiu

Bulgaria grants EUR 587 million to 82 battery storage projects

Bulgaria grants EUR 587 million to 82 battery storage projects

22 April 2025 - Developers of 82 standalone battery projects in Bulgaria, for an overall 9.71 GWh in capacity, got approval for EUR 587 million in subsidies

bih energoinvest transformers brand tuzla

Energoinvest inaugurates transformers made in BiH

22 April 2025 - Bosnia and Herzegovina-based company Energoinvest has manufactured the first domestic transformers under its brand

Bulgaria canceling sale equipment Belene nuclear plant Ukraine

Bulgaria canceling sale of equipment for its Belene nuclear plant to Ukraine

22 April 2025 - Bulgaria decided to call off the sale of equipment from the failed Belene nuclear project to Ukraine's Energoatom and reactivate the plans