Croatia’s first utility-scale renewables auctions undersubscribed

croatia first auctions wind solar hrote

Photo: Albrecht Fietz from Pixabay

Published

July 11, 2022

Country

Comments

comments icon

0

Share

Published:

July 11, 2022

Country:

Comments:

comments icon

0

Share

The first auctions in Croatia for awarding premiums for utility-scale renewable power plants resulted in a poor response. Only 19 applications were received for a total capacity of 150 megawatts (MW) while 638 MW was offered.

The Croatian Energy Market Operator (HROTE) announced a public call for premiums on June 17 and investors had until July 4 to send in their bids.

Three bids for an overall 113 MW were received for wind farms, and there were five bids for solar power plants, compared to 300 MW on offer for each technology. For biogas power plants, the quota was 16 MW and the investors sent seven bids for a combined 8.7 MW in capacity.

The quota for hydropower plants (HPPs) was the only one oversubscribed, with three offers for 5.3 MW, and the offer was 4 MW.

The offer for geothermal facilities was met by one bid for a capacity of 10 MW. No bids were received for biomass power plants, and the quota was 8 MW.

The maximum premiums were set in a range from EUR 60 per MWh to almost EUR 200 per MWh

HROTE said it would evaluate the bids within 30 days and pick the winners.

The public call listed the maximum reference values ​​of premiums per megawatt-hour:

  • Solar power plants – HRK 495.63 (EUR 65.47)
  • Wind farms – HRK 460.91 (EUR 60.88)
  • Geothermal power plants – HRK 1,263.96 (EUR 167.95)
  • Biomass power plants – HRK 1,411.57 (EUR 186.45)
  • Biogas power plants – HRK 1,482.23 (EUR 195.78)
  • Hydropower plants – HRK 1,095.58 (EUR 144.71).

Auctions for awarding premiums were introduced in Croatia in mid-2020. The first one, for small projects, was held in early 2021. The authorities recently said another round of auctions would be held, with a total quota of 2,010 MW.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

EU institutions reach deal on CBAM simplification

EU institutions reach deal on CBAM simplification

20 June 2025 - Colegislators in Brussels struck a provisional agreement on simplifying CBAM. There is no delay in scope for countries neighboring the EU.

Serbia nuclear hydrogen deal South Korea KHNP

Serbia preparing nuclear, hydrogen deal with South Korea’s KHNP

20 June 2025 - After contacts with Russia, Slovenia and China and the start of cooperation with France, Serbia is expecting an agreement with South Korea's KHNP

slovenia batteries grants kumer kert

Slovenia to subsidize battery storage for businesses with EUR 17 million

20 June 2025 - New batteries can be combined with existing energy storage or solar power plants, the Ministry of the Environment, Climate and Energy said.

ACER opens applications for traineeship programme

ACER opens applications for traineeship program

20 June 2025 - ACER launched a call for its traineeship program in Ljubljana, Slovenia, inviting motivated and qualified university graduates