Elicio presents two projects: wind farm Alibunar and wind farm Malibunar

Photo: Vetroparkalibunar.rs

Published

February 10, 2017

Country

Comments

comments icon

0

Share

Published:

February 10, 2017

Country:

Comments:

comments icon

0

Share

Representatives of Elicio company held a public presentation of Alibunar and Malibunar wind farms, informing the citizens and land owners in the village of Vladimirovac about the plan and schedule for their construction.

Project manager Marijan Rančić presented the plan for construction and reconstruction of roads, as well as the process of shipping and installing turbines, announced Elicio.

“The support of the citizens is very important to us, so that everything transpires smoothly. Members of our team will be available for contact every day, and a mechanism for complaints will also be established”, said Rančić.

Alibunar project will have a capacity of 42 MW. The wind farm will have 21 turbines made by German Senvion. Necessary permits have been obtained, as well as the temporary status of privileged power producer, while obtaining the license for the power transmission line is being obtained in cooperation with Elektromreže Srbije (EMS).

Construction is expected to start in the second half of this year. The expected annual production of electricity is 113.109 MWh, and the value of the investment is EUR 72,64 million.

Malibunar project has the capacity of 8 MW, comprising of four turbines type Senvion M-100. The project has all the necessary permits, temporary status of privileged power producer, signed power purchase agreement with Electric Power Industry of Serbia (EPS) and secured funding.

Construction is set to begin in the following weeks, as soon as weather conditions allow it. Expected annual production is 23.8476 MWh and the investment’s value is EUR 13,8 million.

“The plan is to finish construction of Malibunar wind farm and connect it to the grid by the end of this year, while Alibunar is scheduled for the end of next year. It is hard to give an accurate estimate because the weather affected many factors”, said Danijela Isailović, corporate communications officer at Elicio, for Balkan Green Energy News.

Elicio is a Belgian company that in 2014. took over the projects of Electrawinds company, including Malibunar and Alibunar in Serbia. Elicio is part of Nethys group, an energy and telecommunications giant.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Grzegorz Zieliński lead EBRD s South Eastern Europe

Grzegorz Zieliński to lead EBRD’s operations in South‑Eastern Europe

19 May 2026 - EBRD's new Managing Director for South‑Eastern Europe Grzegorz Zieliński is assuming the office at the beginning of next month, succeeding Charlotte Ruhe

No silver bullet decarbonizing energy intensive industries low-hanging fruits Belgrade Energy Forum 2026

‘No silver bullet’ for decarbonizing energy-intensive industries, but there are low-hanging fruits

19 May 2026 - While there is no silver bullet for the decarbonization of energy-intensive industries, there are some low-hanging fruits, said the participants of a panel within Belgrade Energy Forum – BEF 2026

serbia eu region bef 2026 cbam border eu western balkans

CBAM may hinder decarbonization and renewables, contrary to its intended aim

18 May 2026 - The European Union’s Carbon Border Adjustment Mechanism (CBAM) has caused serious disruptions to electricity markets...

NGEN Smart batteries AI are energy transition bedrock

NGEN: Smart batteries, AI are energy transition bedrock

18 May 2026 - The energy system of the future is decentralized, dynamic, and software-controlled, NGEN Group's representatives pointed out at BEF 2026