Renewables

Elicio presents two projects: wind farm Alibunar and wind farm Malibunar

Photo: Vetroparkalibunar.rs

Published

February 10, 2017

Country

Comments

comments icon

0

Share

Published:

February 10, 2017

Country:

Comments:

comments icon

0

Share

Representatives of Elicio company held a public presentation of Alibunar and Malibunar wind farms, informing the citizens and land owners in the village of Vladimirovac about the plan and schedule for their construction.

Project manager Marijan Rančić presented the plan for construction and reconstruction of roads, as well as the process of shipping and installing turbines, announced Elicio.

“The support of the citizens is very important to us, so that everything transpires smoothly. Members of our team will be available for contact every day, and a mechanism for complaints will also be established”, said Rančić.

Alibunar project will have a capacity of 42 MW. The wind farm will have 21 turbines made by German Senvion. Necessary permits have been obtained, as well as the temporary status of privileged power producer, while obtaining the license for the power transmission line is being obtained in cooperation with Elektromreže Srbije (EMS).

Construction is expected to start in the second half of this year. The expected annual production of electricity is 113.109 MWh, and the value of the investment is EUR 72,64 million.

Malibunar project has the capacity of 8 MW, comprising of four turbines type Senvion M-100. The project has all the necessary permits, temporary status of privileged power producer, signed power purchase agreement with Electric Power Industry of Serbia (EPS) and secured funding.

Construction is set to begin in the following weeks, as soon as weather conditions allow it. Expected annual production is 23.8476 MWh and the investment’s value is EUR 13,8 million.

“The plan is to finish construction of Malibunar wind farm and connect it to the grid by the end of this year, while Alibunar is scheduled for the end of next year. It is hard to give an accurate estimate because the weather affected many factors”, said Danijela Isailović, corporate communications officer at Elicio, for Balkan Green Energy News.

Elicio is a Belgian company that in 2014. took over the projects of Electrawinds company, including Malibunar and Alibunar in Serbia. Elicio is part of Nethys group, an energy and telecommunications giant.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

europe solarpower Startup Awards 2026 reLi Energy

ReLi energy wins first prize at European Solar Startup Awards 2026

07 May 2026 - Germany’s reLi Energy won gold at the European Solar Startup Awards 2026. It has outperformed three other finalists to claim the top spot

greece public cooperative solar power plant Western Greece aetolia

Greece to install largest public cooperative solar park for farmers, vulnerable households

07 May 2026 - The Greek authorities plan to install a cooperative solar power plant for the supply of 147,000 farmers and 17,000 vulnerable households

Rezolv Energy 225 MW solar park St. George in Bulgaria

Rezolv Energy commissions 225 MW solar park St. George in Bulgaria

07 May 2026 - One of Bulgaria’s largest solar parks is now fully operational. Rezolv Energy built the St. George facility on the site of the former Silistra airport.

epcg projects milutin đukanovic

Montenegrin utility EPCG developing 639 MW of power generation and storage projects

06 May 2026 - EPCG is developing solar, wind, battery, and hydropower projects totaling 639 MW, with an expected annual output of over 1 TWh, wrote Milutin Đukanović, President of the Board of Directors