Renewables

Elicio presents two projects: wind farm Alibunar and wind farm Malibunar

Photo: Vetroparkalibunar.rs

Published

February 10, 2017

Country

Comments

comments icon

0

Share

Published:

February 10, 2017

Country:

Comments:

comments icon

0

Share

Representatives of Elicio company held a public presentation of Alibunar and Malibunar wind farms, informing the citizens and land owners in the village of Vladimirovac about the plan and schedule for their construction.

Project manager Marijan Rančić presented the plan for construction and reconstruction of roads, as well as the process of shipping and installing turbines, announced Elicio.

“The support of the citizens is very important to us, so that everything transpires smoothly. Members of our team will be available for contact every day, and a mechanism for complaints will also be established”, said Rančić.

Alibunar project will have a capacity of 42 MW. The wind farm will have 21 turbines made by German Senvion. Necessary permits have been obtained, as well as the temporary status of privileged power producer, while obtaining the license for the power transmission line is being obtained in cooperation with Elektromreže Srbije (EMS).

Construction is expected to start in the second half of this year. The expected annual production of electricity is 113.109 MWh, and the value of the investment is EUR 72,64 million.

Malibunar project has the capacity of 8 MW, comprising of four turbines type Senvion M-100. The project has all the necessary permits, temporary status of privileged power producer, signed power purchase agreement with Electric Power Industry of Serbia (EPS) and secured funding.

Construction is set to begin in the following weeks, as soon as weather conditions allow it. Expected annual production is 23.8476 MWh and the investment’s value is EUR 13,8 million.

“The plan is to finish construction of Malibunar wind farm and connect it to the grid by the end of this year, while Alibunar is scheduled for the end of next year. It is hard to give an accurate estimate because the weather affected many factors”, said Danijela Isailović, corporate communications officer at Elicio, for Balkan Green Energy News.

Elicio is a Belgian company that in 2014. took over the projects of Electrawinds company, including Malibunar and Alibunar in Serbia. Elicio is part of Nethys group, an energy and telecommunications giant.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

france wind offshore auction cybersecurity

France favors European-made components in wind and solar auctions, plans cybersecurity criterion

06 April 2026 - France has launched a 12 GW renewable energy auction package that will favor bids using a higher share of European-made technology

montenegro epcg edf hpp krusevo sahmanovic dragas mrvaljevic

Montenegro, EDF discuss Kruševo pumped storage hydropower project

06 April 2026 - Representatives of the Ministry of Energy and Mining and state-owned power utility Elektroprivreda Crne Gore held talks with EDF's delegation

PPC Group 2 13 GW photovoltaics including EU second largest solar park

PPC Group completes 2.1 GW of photovoltaics including EU’s second-largest solar park

06 April 2026 - Public Power Corp. said its new PV cluster is the biggest in Europe. It includes Phoebe, the second-largest solar park in the European Union.

Solar dominated Greek PPA contracts in 2025

Solar dominates Greek PPA contracts in 2025

06 April 2026 - The Hellenic Energy Exchange (HEnEx) published its annual report for 2025, including data on PPAs as part of its dedicated digital platform