Electricity distribution operator Oshee received procurement procedure applications for the construction of the 20 kV network Paskuqan – Babrru No. 2, Investment.albaniaenergy.org portal reported. The procurement came after the open notice released on April 8 for the construction of 20kV Paskuqan – Babru network No. 5, with April 30 as deadline for prequalification submission, and the open notice for network No. 3 with deadline on May 8. The procurement’s limit fund is established at ALL 222.15 million (EUR 1.59 million) plus value-added tax and with the incomes from operating expenses. The deadline for completion of works is five months.