Evia wind farm investors given extension to pay for cable connection

Photo: Pixabay

Published

December 22, 2016

Country

Comments

comments icon

0

Share

Published:

December 22, 2016

Country:

Comments:

comments icon

0

Share

Investors in the wind energy parks on Evia island are given two-month extension to start paying for the cost of underwater cable connection linking Polypotamos in Evia with the outskirts of the Greek capital Athens.

The group of investors holding licenses for the construction of the wind farms in the southern part of Evia, were expected to start paying the submarine cable connection’s cost by the end of this year, Energy Press reported.

This extension was made possible by an energy ministry bill amendment submitted to Greek Parliament as a result of cash flow problems being encountered in the RES sector.

Approximately fifteen investors holding wind facility licenses for southern Evia will need to pay IPTO, the power grid operator, for the connection project’s cost, estimated at 80 million euros. The line has a 400-MW capacity.

Major wind energy investors in Greece such as PPC, Terna, Enteka, Gamesa, Iberdrola, and Protergia plan to develop projects in the southern part of the Evia island.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

bih federation ephzhb court poklecani urban permit arhaus

Supreme Court of Federation of BiH annulls urban permit for Poklečani wind farm

17 April 2025 - The project is being developed by Elektroprivreda HZHB, one of the three state-owned power utilities in Bosnia and Herzegovina

Minister Admir Sahmanović formally assumes energy, mining portfolio in Montenegro

Minister Admir Šahmanović formally assumes energy, mining portfolio in Montenegro

17 April 2025 - Minister of Energy and Mining of Montenegro Admir Šahmanović was formally voted in as the two ministries that he ran were merged

Nofar Energy 265 MW solar power plant Corbii Mari near Bucharest

Nofar Energy inks deal for 265 MW solar power plant near Bucharest

17 April 2025 - The operator of the biggest solar power plant in Romania is about to start building a much bigger facility in Corbii Mari

romania omv petrom ce oltenia girisim Ameresco Sunel

OMV Petrom, CE Oltenia pick contractors for four solar power plants

17 April 2025 - OMV Petrom and Complexul Energetic Oltenia (CE Oltenia) have signed design and installation contracts for four solar power plants