Petrović: ERS to launch construction of Trebinje 3, Hrgud this year

bih ers luka petrovic trebinje solar hrgud wind

Luka Petrović (photo: ERS)

Published

January 20, 2026

Comments

comments icon

0

Share

Published:

January 20, 2026

Comments:

comments icon

0

Share

Power utility Elektroprivreda Republike Srpske plans to start the installation of the Trebinje 3 solar power plant and the Hrgud wind farm this year, according to CEO Luka Petrović.

Elektroprivreda Republike Srpske (ERS) already has projects in a ready-to-build phase through its subsidiary companies, Luka Petrović explained, Srpskainfo reported.

ERS is the dominant power producer and supplier in the Republic of Srpska, one of the two entities constituting Bosnia and Herzegovina.

The Trebinje 3 solar power plant, with a capacity of 53 MW, will be built first. The company has received a concession from the Government of the Republic of Srpska. The tender for construction will be launched soon, Petrović stressed.

Preparations for the Hrgud wind farm are also in the final stages, he added. Multi-year wind potential assessments and environmental studies have been completed. Petrović anticipates the start of construction this year. The planned capacity is 60 MW.

Wind energy attracts the most attention in the Republic of Srpska

The installation of the two power plants is expected to be finished by the end of 2027 or in early 2028, he asserted. The CEO added they would significantly contribute to the development of renewable energy sources.

He noted that wind energy attracts the most attention in the entity. The concessions commission of the Republic of Srpska has also awarded approvals for the construction of more than 1,200 MW of photovoltaic plants, Petrović recalled.

In his view, investments by private firms are dormant because solar power production is no longer profitable without battery energy storage systems (BESS).

Petrović: Many solar projects will not be completed

Solar energy prices are significantly lower than they were four to five years ago, Petrović added.

Many of these solar projects will not be finished, he underscored.

Of note, ERS decided late last year to revive the Hrgud wind project, which was halted after a decision by the German government.

The concession for the Trebinje 3 solar power project was awarded in April 2025.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

europe verbund nordex Dietmar Reiner José Luis Blanco agreement

From Austria to Albania: Verbund, Nordex to deploy 105 wind turbines across Europe

20 January 2026 - Verbund Green Power has entered into a multiyear framework agreement with leading wind turbine producer Nordex Group

bih ers luka petrovic trebinje solar hrgud wind

Petrović: ERS to launch construction of Trebinje 3, Hrgud this year

20 January 2026 - Elektroprivreda Republike Srpske already has projects in a ready-to-build phase through its subsidiary companies, Luka Petrović explained

eet virtual meter electricity

Austrian EET rolls out AI-powered device to simplify home electricity metering

20 January 2026 - The metering device called the Virtual Meter deduces and delivers the entire home's electricity consumption data in under one second

KOSTT takes over land in Kosovo for battery system in US-funded project

KOSTT takes over land in Kosovo* for battery system in US-funded project

20 January 2026 - KOSTT obtained the 2.3 hectares of land for its 45 MW battery project, funded by Millennium Challenge Corp. of the United States