Hydropower plant Dabar to be completed by end-2027

bih republic of srpska hydropower dabar HPP petar djokic

Photo: Ministry of Energy and Mining

Published

September 29, 2025

Comments

comments icon

0

Share

Published:

September 29, 2025

Comments:

comments icon

0

Share

The Dabar hydropower plant is expected to be completed by the end of 2027, according to Petar Đokić, Minister of Energy and Mining of the Republic of Srpska.

The operation of the Dabar hydropower plant, the most complex hydropower facility, in which EUR 339.5 million has been invested, will bring benefits for the entire eastern Herzegovina area, Petar Đokić said during a visit to the construction site, Srna reported.

The works on the 160 MW hydropower plant, with an expected annual production of 500 GWh, began in June 2023.

Đokić noted that the project is located in four municipalities – Nevesinje, Bileća, Berkovići, and Ljubinje – spanning 40 kilometers. As a key part of the project, Đokić highlighted a 12-kilometer tunnel, which is nearly finished.

Đokić: It is an exceptional construction undertaking, the first of its kind in the world in the 21st century

It is an exceptional construction undertaking, the first of its kind in the world in the 21st century, the minister said and added that he is proud to be part of the project from the beginning of its implementation.

bih republic of srpska hydropower dabar djokic
Photo: Ministry of Energy and Mining

He spoke with the representatives of China-based Gezhouba Group Co., the main contractor, and Integral and Elnos, its domestic subcontractors.

Đokić stressed that some issues regarding the construction were discussed. HPP Dabar is a financially demanding project, he noted.

bih republic of srpska hydropower dabar HPP djokic
Photo: Ministry of Energy and Mining

Wind farm Grebak will be completed by 2027

Minister Đokić recalled that projects for solar power plants and wind farms with a capacity of 680 MW are under development in the territory of Nevesinje municipality, with investments estimated at an overall EUR 409 million.

He underlined that one of the projects, the Grebak wind farm, has experienced delays. Numerous companies, including the investor in the Grebak project, are hostages to the European policies mistrustful of Bosnia and Herzegovina, Đokić claimed.

Of note, the Republic of Srpska is one of the two political entities of BiH. The concession for the Grebak wind farm was granted in April 2019.

The minister expressed hope that the investor would overcome the challenges, conclude a financing agreement, secure equipment, and start construction work, expected to be finished by late 2026 or early 2027.

Investors in solar projects in Nevesinje are currently preparing documentation and purchasing equipment, Đokić said.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Kelag International RES Project - WPP Jasenice and SPP Bukovica near Zadar, Croatia

Kelag International strengthens European presence with brand unification

08 January 2026 - Kelag International has unified its subsidiaries under its single brand, saying it is strengthening the group’s European identity

slovenia snow solar panels

Why nobody in Slovenia bothers to remove snow from solar panels

08 January 2026 - Slovenian solar power plant operators are not attempting to remove snow from panels, as doing so would cause more harm than good

New auction announced in Greece for 600 MW in self-consumption projects

New auction announced in Greece for 600 MW for electricity for vulnerable households

08 January 2026 - The Greek government specified the conditions for a renewable energy auction. The Apollo initiative is aimed at reducing costs for vulnerable households.

eu western balkans cbam electricity market amendments

EU’s amendments to CBAM: possibility of relief, but January 1 brought market uncertainty

06 January 2026 - Long-awaited implementing acts and amendments to the CBAM Regulation brought only a minor relief for...