Renewables keep top spot in Greece’s power mix despite surge in curtailments

curtailments wind farm renewables greece

Photo: ELG21 from Pixabay

Published

August 6, 2025

Country

Comments

comments icon

0

Share

Published:

August 6, 2025

Country:

Comments:

comments icon

0

Share

Renewable energy sources continued to rank first in Greece’s electricity mix despite significant curtailments in the first half of 2025, which more than doubled against the same period a year earlier. At the same time, gas-fired power generation hit a 10-year high, while coal’s share in covering domestic demand fell to the lowest level in at least a decade, according to a recent analysis by the Green Tank.

In the year through June, curtailments totaled 1,327 GWh, equivalent to 9.6% of Greece’s overall renewables output, compared to 513 GWh in the same period last year and 899 GWh in the whole of 2024.

Curtailments in June 2025 reached 351.7 GWh, which means renewable energy generation could have been 12.3% higher. The level compares to only 59.5 GWh, or 2.5%, rejected in June 2024. Most curtailments in June occurred between 10 am and 3 pm, with the highest daily amount, of 32.7 GWh, recorded on June 1.

In May 2025, curtailments were 382.5 GWh, up from 127.3 GWh a year earlier, and in April they totaled 359.1 GWh, compared to 253.3 GWh in the same month of 2024. In March, the grid rejected 229 GWh of renewable electricity, up from 73.3 GWh in March 2024, while curtailments in February and January amounted to 3.4 GWh and 1.3 GWh, respectively, compared to zero in the first two months of 2024.

Renewables covered 46% of Greece’s electricity demand in H1 2025

Greece’s electricity demand in the first half of 2025 reached 27,038 GWh, with renewables covering 46%. The only equivalent period so far when the share was higher was last year. In June, electricity demand jumped 22% against May, to 5,094 GWh. The average market price remained low, at EUR 85.4 per MWh, the Green Tank noted.

Renewables ranked first in electricity generation in H1 2025, with a total of 12,435 GWh, a marginal increase from 12,354 GWh in H1 2024.

Gas-fired power generation reached 10,925 GWh in the first half of 2025 or 19.3% more than one year before, hitting a 10-year high. The rise was mostly driven by an increase in net exports and electricity demand. A drop in output in the segments of hydropower lignite and oil also contributed, together with an expansion of the gas power fleet.

Gas covered 40.4% of electricity demand in the first six months of the year, after 34.1% in the comparable period of 2024.

Coal power production fell steadily from January to June

Coal, on the other hand, covered just 5.2% of Greece’s power demand in H1 2025. It was the lowest share in at least a decade. Electricity production from lignite declined steadily in the first six months of the year, from 511 GWh in January to just 66 GWh in June.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

IPS International Power Supply inaugurates Bulgaria first battery gigafactory

International Power Supply inaugurates Bulgaria’s first battery gigafactory

13 October 2025 - International Power Supply (IPS) opened its Factory X1 on the outskirts of Sofia, with a capacity of 3 GWh per year

ie energy bess smart battery storage

Croatian IE-Energy, Slovenia’s NGEN plan virtual network of smart battery storage systems

10 October 2025 - The EUR 60 million project is a step toward creating a virtual network of battery storage systems connecting renewable energy producers and consumers.

bih republic of srpska cbam petar djokic

Đokić: We expect EU to accept request to postpone CBAM implementation

10 October 2025 - Minister of Energy and Mining of the Republic of Srpska expressed belief that the European Commission would postpone the implementation CBAM

north macedonia batteries BESS solar wind natural gas investments sanja bozinovska

North Macedonia receives applications for 4.2 GW of battery projects

10 October 2025 - October 1 was the deadline for foreign investors interested in the construction of power plants to submit their initiatives