Solaris Holding launches production at large hybrid renewable energy park in Bulgaria

Solaris Holding large hybrid renewable energy park Bulgaria

Photo: Solaris Holding

Published

July 2, 2025

Country

Comments

comments icon

1

Share

Published:

July 2, 2025

Country:

Comments:

comments icon

1

Share

The new Selanovtsi solar farm of 59.8 MW in peak capacity near Vratsa was installed alongside a battery energy storage system of 107.3 MWh in capacity. The hybrid energy park, owned by Solaris Holding, is now accumulating the midday output and releasing it into the grid at hours of increased demand.

Engineering, supply and construction company Solaris Holding, a joint venture of the Bulgarian-German Sunotec and the main shareholders of Eurohold Bulgaria (Evrohold), launched the operation of a hybrid power plant in the municipality of Oryahovo in Vratsa district. The project in the country’s northwest is financed by United Bulgarian Bank (UBB or OBB) and the German Varengold Bank.

The Selanovtsi solar power plant’s peak capacity is 59.8 MW. It is integrated with a new battery energy storage system (BESS) of 107.3 MWh. Annual output is estimated at 79.9 GWh. It is equivalent to the energy needs of more than 22,000 households and it saves more than a million tons of carbon dioxide emissions, according to the developer.

Electrohold Trade, part of Electrohold Group and Eurohold, is responsible for the sale of electricity.

Hybrid power plant generating 79.9 GWh per year

The Selanovtsi facility, located near an eponymous village, spans 37.9 hectares. It consists of 103,116 solar modules. A team of 250 people built the hybrid renewable energy park, which features lithium-ion-phosphate (LFP) batteries, according to the update.

During the hours of lower consumption, the integrated system stores the green energy and delivers it to the grid around the daily demand peaks. It ensures a more balanced load on the electricity system, increases its stability and efficiency, and contributes to a more reliable integration of renewable sources into the national grid, the statement adds.

Solaris has four even larger projects underway

Solaris plans to commission four more battery-powered photovoltaic plants, even larger in size. In September, it inaugurated a hybrid solar power and storage facility in Pernik.

BESS has become a standard element of PV projects in Bulgaria. In addition, the country’s battery manufacturing capacity is growing and the government has completed its tenders for state support to BESS combined with renewable energy plants, and for standalone units. But even before the subsidies, there are facilities under construction.

Comments (1)
Elias Hossain / July 18, 2025

I am Bangladeshi, now doha Qatar, working shuttering Carpenter steel fixer, i am interested to work bulgeria constitution company, i am poor to bear visa expensive and others

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

CJR Renewables 102 MW Urleasca wind farm Romania

CJR Renewables completes construction of 102 MW Urleasca wind farm in Romania

09 October 2025 - The Urleasca wind farm in Brăila county in eastern Romania is complete, contractor CJR Renewables said

slovenia coal phaseout coal mine velenje golob robert visit

Slovenia begins preparations for closure of Velenje coal mine

09 October 2025 - Slovenian Prime Minister Robert Golob visited the Velenje coal mine to present a draft law on its gradual closure

Metlen Karatzis Greece largest battery joint venture

Karatzis, Metlen to install Greece’s largest battery in joint venture

09 October 2025 - Metlen and Karatzis Group of Companies are establishing a joint venture for a standalone BESS of 330 MW and 790 MWh

world dnv energy transition energy transition outlook 2025

Policy changes in US will have marginal impact on global energy transition

09 October 2025 - AI energy use may seem alarming, but it is projected to stay below EV charging and the cooling of buildings, DNV calculated