Electricity

Court ruling brings risk of reversal of power market liberalization in Kosovo*

Court ruling risk reversal power market liberalization Kosovo

Photo: iStock

Published

June 25, 2025

Country

Comments

comments icon

0

Share

Published:

June 25, 2025

Country:

Comments:

comments icon

0

Share

The Commercial Court in Kosovo* supported the claims filed by one company in a complaint, suspending its obligation to purchase electricity in the free market. The ruling follows protests against the controversial liberalization of the power market for larger firms, which came into force on June 1.

Two old coal-fired power plants in Kosovo* account for 92% of domestic production, which is the highest level in the world. Outages often prompt expensive emergency imports of electricity. Just last week, all operational coal units malfunctioned, while one in Kosovo B has been under reconstruction since last month.

Nevertheless, the authorities pushed through a controversial liberalization of the market for companies with more than 50 employees or an annual turnover of more than EUR 10 million. The measure, which came into force on June 1, led to two large protests. Almost 1,300 firms must purchase electricity in the free market.

However, the Commercial Court in Kosovo* suspended the obligation for REKS in a recent first-degree ruling. The company filed a complaint after it wasn’t allowed to use universal supply. It argued that it faced irreversible financial damage.

KEK signs few commercial power purchase contracts

The designated supplier of last resort is government-controlled Kosovo Energy Corp. (KEK). It is the operator of the Kosovo A and Kosovo B coal plants. Corporate consumers can opt for contracts of up to six months with the supplier of last resort.

KEK said a week ago that 360 such deals have been signed and that another 540 were coming. It only had 16 commercial contracts until that point.

Kosovo Chamber of Commerce claims KESCO is favored in liberalization

In the interpretation of the Kosovo Chamber of Commerce (KCC or OEK), the new court ruling means the entire power market liberalization needs to be suspended.

Conversely, the Energy Regulatory Office (ERO) said that last week the Basic Court of Prishtina rejected the motion that the chamber filed challenging the regulator’s public notice on the matter, which it issued in March.

KCC suggested that KESCO was favored in the switch, citing the lack of offers to consumers from other power suppliers. Dozens of other companies have also filed complaints, it added. The chamber called for a fair and feasible transitional phase and the creation of a clear plan that would ensure the stability for businesses and citizens.

Also of note, the Commercial Court said REKS’s gross income last year amounted to just EUR 6.5 million.

In other news, the opposition Democratic Party of Kosovo (PDK) said it would challenge ERO’s decision at the Basic Court because of the potential increase in electricity prices due to the liberalization.

* This designation is without prejudice to positions on status and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Serbia developing legal framework for CO2 storage

Serbia developing legal framework for CO2 storage

08 January 2026 - Serbia's draft law on hydrocarbon exploration and exploitation will include permanent disposal of CO2 in geological formations of depleted deposits

Kelag International RES Project - WPP Jasenice and SPP Bukovica near Zadar, Croatia

Kelag International strengthens European presence with brand unification

08 January 2026 - Kelag International has unified its subsidiaries under its single brand, saying it is strengthening the group’s European identity

slovenia snow solar panels

Why nobody in Slovenia bothers to remove snow from solar panels

08 January 2026 - Slovenian solar power plant operators are not attempting to remove snow from panels, as doing so would cause more harm than good

New auction announced in Greece for 600 MW in self-consumption projects

New auction announced in Greece for 600 MW for electricity for vulnerable households

08 January 2026 - The Greek government specified the conditions for a renewable energy auction. The Apollo initiative is aimed at reducing costs for vulnerable households.