Renewables

ELEM activates EUR 5.6 million in guarantees from Slovenia’s Riko

Photo: Pixabay

Published

April 14, 2015

Comments

comments icon

0

Share

Published:

April 14, 2015

Comments:

comments icon

0

Share

The bank guarantees provided by Slovenia’s Riko worth EUR 5.6 million were activated, state-owned power producer ELEM said on April 9. The foreign company failed to meet obligations in the former Yugoslav republic on the construction of a 36.4 MW hydropower plant (HPP), said ELEM, operator of the facility.

St. Petka HPP was officially delivered on a turnkey basis on February 5, 2013, but some of the works which were specified in the tender documentation were not completed within the prescribed period and their quality did not meet the contractor’s requirements, ELEM said in a statement emailed to SeeNews.

Furthermore, Riko failed to remove some of the faults in the HPP’s operation which were identified during the trial period, Energia.gr portal reported. ELEM also said that St. Petka was delivered 270 days later than agreed, which entails penalties in the amount of 10% of the contract value. The construction of the plant was due to be completed by April 2009.

Hydro plant St. Petka’s annual production is 66 GWh of electricity. The project was worth 75 million euro, the Macedonian government said earlier. ELEM operates two thermal power plants and eight hydropower plants.

Tags: , ,

Related Articles

Turkish geothermal power plant operator drill for geothermal lithium

Turkish renewables firm to drill for geothermal lithium

26 July 2025 - Margün Energy intends to search for lithium in geothermal water in western Turkey, where it took over a 12 MW geothermal power plant

serbia wind farm plandiste nis met dubravka djedovic

Government of Serbia interested in taking over Plandište wind project

25 July 2025 - Plandište is one of the projects that obtained feed-in tariffs under the first quota of 500 MW for wind power plants in Serbia

Over 20,000 prosumer projects connected in Greece during last 18 months

Over 20,000 prosumer units connected in Greece in last 18 months

24 July 2025 - Households and businesses remain highly interested in becoming prosumers in Greece, although the new net billing program faces delays.

Project 81 MW solar park on coal mine in Montenegro

Project underway for 81 MW solar park on coal mine in Montenegro

24 July 2025 - The Government of Montenegro gave a provisional green light for a solar power plant of 81.1 MW in peak capacity on coal land in Pljevlja