Electricity

Race against time for Greece to avoid a blackout on Easter

Race against time for Greece to avoid a blackout on Easter

Photo: freepik.com

Published

February 18, 2025

Country

Comments

comments icon

0

Share

Published:

February 18, 2025

Country:

Comments:

comments icon

0

Share

Greek authorities are rushing to secure the electricity system against a possible blackout during Easter.

Greece currently produces much more electricity than it needs on certain days due to a high renewables penetration and insufficient energy storage. It should be noted that in 2024 the country became a net power exporter for the first time after two decades. Usually, extra power is no problem, as it is exported and curtailments ensure nominal system operation with no danger of a blackout.

However, this year there will be days when low demand combined with high renewable electricity production creates a problem. At Easter, demand traditionally craters.

Independent Power Transmission Operator (IPTO or Admie) estimates that on Easter Sunday the country’s interconnections would operate near their maximum safety limits. If even a single line goes offline, it would lead to a domino effect and the possible loss of all the connections with neighboring countries. As a result, the frequency will rise beyond safe limits in the Greek system, triggering the desynchronization of power plants and a blackout.

To avoid such a scenario, authorities have imposed adding telemetry systems in recent months to photovoltaic units of over 400 kW connected to the distribution network. Currently, the Hellenic Electricity Distribution Network Operator (HEDNO or DEDDIE) can curtail 1.9 GW of solar power capacity, but another 6 GW is unswitchable.

Telemetry must be enabled by April in small PV units

A deadline was given until February 13 to the owners within the latter category to add telemetry equipment so that HEDNO can curtail their production when needed. However, very few complied and the rest said they are still waiting for the systems to be delivered.

HEDNO estimates that 5,700 plants with capacities of 400 kW to 1 MW must be added to curtailments, as well as 600 plants with more than 1 MW apiece.

Based on the above, owners of solar power units and the two grid operators must add the ability by April to ensure system stability.

Gradual installation of energy storage facilities is expected to help significantly and bring curtailments down.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

serbia solar wind 2025 projections

Serbia to add 138 MW in solar, wind in 2025

21 February 2025 - The estimated capacity of prosumers is 123.6 MW, out of which 43 MW would be new photovoltaics, according to the energy balance

Energy industry confidence in net-zero goals sinks EIC report

Energy industry confidence in net zero goals sinks – report

21 February 2025 - Energy industry confidence in reaching net zero targets is fading, according to Net Zero Jeopardy Report II by the Energy Industries Council

EU renewables role Vision for Agriculture and Food

EU acknowledges renewables role in Vision for Agriculture and Food

21 February 2025 - Green energy and energy communities are beneficial for farmers, the European Commission said in its Vision for Agriculture and Food

Kosovo four applications wind power auction

Kosovo* receives four applications for wind power auction

21 February 2025 - German, Kosovar, French and Turkish companies submitted documentation to qualify for the first wind power auction in Kosovo*