Greece needs 7 GW of energy storage by 2030 to avoid high curtailments

Greece will need 7 GW of storage by 2030 to avoid high curtailments

Photo: Freepik

Published

July 27, 2024

Country

Comments

comments icon

0

Share

Published:

July 27, 2024

Country:

Comments:

comments icon

0

Share

Up to 20% of renewable electricity production is expected to be curtailed by 2030 in Greece if no new investments are made in energy storage.

Greece is faced with ever-increasing curtailments of renewable energy production. Based on expectations from the revised National Energy and Climate Plan (NECP), an attempt will be made to deal with the issue by encouraging investment in storage.

Curtailments are projected to reach 5% of green energy production by the end of 2024 and increase further to 10% in the following year, according to participants at a recent webinar organized by the Hellenic Association of Photovoltaic Companies (HELAPCO).

The Green Tank said that in absolute terms they have increased from 308 GWh in the first four months of the year to 515 GWh through July. Despite the rise of demand in the summer season, 85 GWh still had to be curtailed in June and July.

It creates a problem not just for renewable energy producers, but also for consumers, who need every cheap electron coming from wind and solar farms to reduce their costs.

Photovoltaics would face 20% curtailments without batteries

Professor Pantelis Biskas from the Aristotle University of Thessaloniki (AUTH) estimates that by 2030 curtailments will affect 15% to 16% of wind power capacity and 20% of photovoltaics.

Revised NECP to set storage goal

The obvious solution is energy storage and the revised NECP is expected to provide visibility for more investments. Biskas said storage must reach 7 GW to 8 GW by 2030 to reduce curtailments to just 2% to 4% and keep energy costs low for consumers. The system requires both batteries and pumped storage hydropower plants.

The exact goal for storage in the final NECP is not yet known. The plan is expected to be submitted for public consultation within the next few weeks by the Ministry of Environment and Energy.

It should be added that Greece has already moved forward with its first 1,000 MW of battery storage systems. So far two auctions have taken place successfully and the first projects are expected to be completed in 2025.

The ministry is still preparing Greece’s third subsidy auction for standalone batteries. The deadline for submissions should apparently be set for early September. Facilities with a four-hour duration can qualify, while the requirement was two hours in the first two rounds. The quota would be 300 MW.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Energy companies confront dual mandate keeping supply secure while accelerating green transition BEF 2026

Energy companies in Western Balkans confront dual mandate – keeping supply secure while accelerating green transition

13 May 2026 - Companies in the region have challenges in energy security, decarbonization and digitalization, and the key is investing in production, the grid and batteries, according to the panel on power system transition at Belgrade Energy Forum 2026

serbia eu region bef 2026 jelena matejic ems renewables grid connection

Matejić: Serbia’s grid to integrate 12 GW of renewables in next six years

12 May 2026 - Jelena Matejić, General Manager of Elektromreža Srbije, took part in a panel on transmission grids at Belgrade Energy Forum 2026

Belgrade Energy Forum 2026 EU support necessary decarbonization Western Balkans

Belgrade Energy Forum 2026: EU’s support necessary for decarbonization in Western Balkans

11 May 2026 - The Western Balkans have progressed in decarbonization and integration with the EU's single energy market, but it must add speed, and with EU's help, top officials agreed at Belgrade Energy Forum 2026 in Serbia

Montenegro EPCG trial run of first wind park Gvozd

Montenegro’s EPCG starts trial run of its first wind park – Gvozd

10 May 2026 - EPCG launched the trial operation of its first wind power plant. Gvozd would be the biggest in Montenegro when the second phase is completed.