Feasibility Study Conclusions on a Regional 400 kV Electricity Interconnection

Published

April 10, 2015

Country

Comments

0

Share

Published:

April 10, 2015

Country:

Comments:

0

Share

The Feasibility Study for the 400 kV Interconnection between Serbia, Montenegro, and Bosnia and Herzegovina has recently been completed, with the cooperation of the electricity system operators in all three countries (EMS, CGES, NOS and Elektroprenos) and the financial support of the European Commission under the WBIF Infrastructure Projects Facility, as well as that of the European Bank for Reconstruction and Development (EBRD) – a prospective financier of the project, according to the press release published on WBIF’s website.

The study investigated the development of a planned interconnection of 400kV amongst Bajina Basta in Serbia, Pljevlja in Montenegro and Visegrad in Bosnia and Herzegovina. The study has analyzed all aspects of the proposed interconnection, (technical, legal and regulatory, economic, market, social etc.) and has demonstrated the project’s feasibility and viability.

The findings of the environmental and social impact assessment (ESIA) indicate that this project can be developed and implemented with little or no disturbance to the environment and to the people who live and work in its surrounding area.

The connection is included in the list of priority projects supported by the Energy Community Secretariat in Vienna as well as in the European Electricity Transmission System Operators Association’s (ENTSO-e) ten-year network development plans for the SEE region.

In the broader context, when this project is complete, it will be part of a strong electricity transmission corridor between Central Serbia and Italy, via the planned undersea cable between Montenegro and Italy.

It is also linked to the previously completed WBIF-funded Feasibility Study on the Western Serbia upgrade (connection between Obrenovac and Bajina Basta) and the Lastva – Pljevlja Feasibility Study in Montenegro, which is now under construction.

Serbia and Montenegro have already taken necessary steps for the completion of this Interconnection by submitting to the WBIF a new joint application for the financing of the detailed design and tender documents associated with the construction works.

Tags: , ,

Related Articles

europe flexibility seasonal balancing iea report

Flexibility needs to be met by demand response, batteries, hydrogen, but also thermal, hydropower plants – IEA

03 May 2024 - The report Managing the Seasonal Variability of Electricity Demand and Supply analyzes the situation in Europe, India, and Indonesia

drina-hydropower-plants

Court annuls environmental permit for Drina hydropower project

02 May 2024 - The construction of large hydropower plants on the Drina is facing new delays, after a court ruling to scrap the environmental permit for HPP Foča

el-dorado-electricity-imports-north-macedonia-rke

North Macedonia: ‘Solar El Dorado’ cuts electricity imports to 2.75%

02 May 2024 - In 2023, North Macedonia's new solar capacity increased by as much as 251% compared to 2022

EU-completing-Green-Deal-Industrial-Plan-Net-Zero-Industry-Act

EU completing Green Deal Industrial Plan as Net Zero Industry Act awaits go-ahead

01 May 2024 - The European Union's Net Zero Industry Act is about to come into force, completing legislative work within the Green Deal Industrial Plan