Feasibility Study Conclusions on a Regional 400 kV Electricity Interconnection

Published

April 10, 2015

Country

Comments

comments icon

0

Share

Published:

April 10, 2015

Country:

Comments:

comments icon

0

Share

The Feasibility Study for the 400 kV Interconnection between Serbia, Montenegro, and Bosnia and Herzegovina has recently been completed, with the cooperation of the electricity system operators in all three countries (EMS, CGES, NOS and Elektroprenos) and the financial support of the European Commission under the WBIF Infrastructure Projects Facility, as well as that of the European Bank for Reconstruction and Development (EBRD) – a prospective financier of the project, according to the press release published on WBIF’s website.

The study investigated the development of a planned interconnection of 400kV amongst Bajina Basta in Serbia, Pljevlja in Montenegro and Visegrad in Bosnia and Herzegovina. The study has analyzed all aspects of the proposed interconnection, (technical, legal and regulatory, economic, market, social etc.) and has demonstrated the project’s feasibility and viability.

The findings of the environmental and social impact assessment (ESIA) indicate that this project can be developed and implemented with little or no disturbance to the environment and to the people who live and work in its surrounding area.

The connection is included in the list of priority projects supported by the Energy Community Secretariat in Vienna as well as in the European Electricity Transmission System Operators Association’s (ENTSO-e) ten-year network development plans for the SEE region.

In the broader context, when this project is complete, it will be part of a strong electricity transmission corridor between Central Serbia and Italy, via the planned undersea cable between Montenegro and Italy.

It is also linked to the previously completed WBIF-funded Feasibility Study on the Western Serbia upgrade (connection between Obrenovac and Bajina Basta) and the Lastva – Pljevlja Feasibility Study in Montenegro, which is now under construction.

Serbia and Montenegro have already taken necessary steps for the completion of this Interconnection by submitting to the WBIF a new joint application for the financing of the detailed design and tender documents associated with the construction works.

Tags: , ,

Related Articles

montenegro italy admir sahmanovic subsea cable solar wind

4 GW of solar, wind projects in pipeline in Montenegro – minister

04 April 2025 - Speaking at the Economic Dialogue Montenegro-Italy round table, minister Admir Šahmanović called for stronger cooperation between the two countries

Share coal power Finland nearly zero cogeneration plant shuts down

Share of coal power in Finland nearly zero as cogeneration plant shuts down

03 April 2025 - The now closed Salmisaari coal plant accounted for just 0.8% of the electricity mix in Finland together with three remaining ones

solar nuclear power prices europe eurelectric

Solar, nuclear lower Europe’s power prices by 30% in March

03 April 2025 - Solar broke a record in power generation in March for the third consecutive month, making up more than 10% of Europe’s electricity mix, Eurelectric said

PPC announces 5.8 billion plan for Western Macedonia, focused on photovoltaics, storage and data centers

PPC plans EUR 5.8 billion makeover of Western Macedonia coal region, including data centers

03 April 2025 - PPC presented a EUR 5.8 billion investment plan for the coal region of Western Macedonia in northern Greece