Turkey aims to almost double electricity generation capacity by 2035

national energy plan Turkey aims double electricity generation capacity 2035

Photo: iStock

Published

January 6, 2023

Country

Comments

comments icon

0

Share

Published:

January 6, 2023

Country:

Comments:

comments icon

0

Share

Turkey’s National Energy Plan for 2035 revealed the ambition to boost solar power capacity by five times and triple the total size of wind power plants. The country intends to increase total electricity generation capacity to 189.7 GW, mostly with renewables. Last year it surpassed the 100 GW threshold.

Turkey published its National Energy Plan for the period until 2035, laying out steps toward reaching the target of net zero greenhouse gas emissions by 2053. The combined capacity of power plants in the country is seen at 189.7 GW. In comparison, the level topped 100 GW early last year. Renewables account for 74.3% of the planned additions.

Green electricity’s share in capacity is projected at 64.7%. Statistics show they accounted for 54% one year ago. The target shows would continue to significantly rely on fossil fuels. Turkey counts on its vast newly discovered offshore gas reserves. Its coal power plant pipeline is one of the biggest in the world.

Nevertheless, expansion in the solar and wind power sectors remains impressive and the country is determined to spur investments in equipment.

Turkey’s goal for solar power for 2035 is 59.9 GW compared to approximately 9 GW of total photovoltaic capacity that it currently hosts.

In 2035, wind power plants should have a combined 29.6 GW, the document reads, of which 5 GW would be offshore. It implies almost tripling the capacity as in 2022 the gauge topped 11 GW. The goal for solar power is 59.9 GW. Turkey currently hosts approximately 9 GW of photovoltaic capacity.

Hydropower plants now have the largest share. They are planned to grow to 35.1 GW in total by 2035, compared to 31.5 GW as of last March. The first segment of Turkey’s first nuclear power plant Akkuyu is scheduled to be commissioned this year. The National Energy Plan aims at a total nuclear energy capacity of 7.2 GW at the end of the period.

Annual electricity consumption is expected to grow 3.5% per year until 2035 to hit 510.5 TWh.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Serbia drafts just transition action plan public debate

Serbia drafts just transition action plan

30 May 2025 - The Ministry of Mining and Energy has published a draft just transition action plan and launched a public debate

Regional Power Sector Exchange Western Balkans disitribution system operator dso grids ohrid giz

Third Regional Power Sector Exchange in Ohrid: Power grids at core of energy transition

30 May 2025 - The third Regional Power Sector Exchange of the Western Balkans gathered over 80 energy professionals from the Western Balkans

two solar power plants egesa enerji vojvodina

Turkish Egesa Enerji to build two solar power plants in Serbia’s Vojvodina province

30 May 2025 - Turkish company Egesa Enerji has launched a project to build two solar power plants in Vojvodina, with a total nominal capacity of 8.6 MW

Green for Growth Fund partnership Swedish International Development Cooperation Agency Sida

Green for Growth Fund launches partnership with Swedish International Development Cooperation Agency

30 May 2025 - GGF and the Swedish International Development Cooperation Agency are expanding green lending in the Western Balkans and the EU's Eastern Neighborhood