The Çetin power plant in Turkey, which saw construction works suspended in February, is up for sale by its Norwegian developer. State-owned Statkraft said it is hiring Garanti Securities as a financial advisor in the bidding process, with a deadline for expressions of interest expiring on August 1.

As fights between government forces and the rebels intensified in southeastern Turkey, Statkraft has stated in its quarterly results it decided to halt most of the construction works on the Botan river. The two facilities planned for total capacity of 517 MW are the Norwegian company’s biggest project outside the home market. It is located in provinces of Siirt and Bitlis. Statkraft said at the time it wrote off NOK 2.09 billion (EUR 220 million) from assets.

The system, which had a third of the works completed, consists of the main plant of 401 MW and the 116 MW unit six kilometres downstream. The company gained control over the project when it acquired 95% of Turkish operator Yeşil Enerji from Global Yatırım in 2009.

Related Articles

EUSEW - Selected Young Energy Ambassadors

EUSEW selects this year’s Young Energy Ambassadors

07 May 2024 - As part of the European Sustainable Energy Week (EUSEW), a new class of Young Energy Ambassadors has been selected

Carbon capture still no alternative decarbonizing cement industry

Carbon capture still has no alternative for decarbonizing cement industry

07 May 2024 - Cement has no credible alternatives for decarbonization without carbon capture, utilization and storage (CCUS), Carbon Tracker found

Turkey-based-Yildirim-109-MW-solar-park-Kosovo-ferronickel

Turkey-based Yıldırım building 109 MW solar park in Kosovo* for its ferronickel plant

07 May 2024 - Yıldırım Energy marked the start of construction works on a 150 MW solar farm in Kosovo*. It will supply the group's ferronickel plant.

BIG Mega Renewable Energy secures financing for landmark Urleasca wind farm in Romania

BIG Mega Renewable Energy secures financing for landmark Urleasca Wind Farm in Romania

07 May 2024 - BIG Mega Renewable Energy, a leading renewable energy developer, has successfully secured financing for the construction and operation of its landmark Urleasca Wind Farm in Romania