Bulgarian system operator plans to connect 4.5 GW of new capacities by 2024

ESO to be fit to connect 4,500 MW of new power plants by 2024

Photo: Jens Rasch from Pixabay

Published

June 3, 2022

Country

Comments

comments icon

0

Share

Published:

June 3, 2022

Country:

Comments:

comments icon

0

Share

By the end of 2024, Bulgaria’s Electricity System Operator (ESO) will finish all the investments needed to secure the connection of new power plants with a total installed capacity of 4,500 MW, primarily renewables.

ESO, the country’s transmission system operator, has invested more than EUR 25 million in the digitalization of the grid, its Executive Director Angelin Tsachev said, as quoted by BTA.

He said the digitalization of the medium-voltage grid is expected to be finished by 2024. The deadline was mid-2026, but the activities were implemented much faster.

Grid modernization is necessary for the company to meet its obligations from all the contracts for connecting new power plants, Tsachev said at the regional conference for renewable energy RE-Source Southeast.

Bulgaria’s TSO plans to increase the cross-border transmission capacity by 2,000 MW

ESO has signed preliminary agreements for 4,000 MW, and it must secure the connection for 4,500 MW, according to the target set in the National Recovery and Resilience Plan.

Tsachev said ESO would be responsible for all new renewable power plants.

The plan also sets a goal to increase the cross-border transmission capacity by 2,000 MW. Bulgaria has already finished its part of the new power line with Greece, Tsachev said.

A new power link with Greece will be constructed by 2023

Greece needs to build the remaining 29 kilometers of the new interconnector with a total length of 122 km. The expected go-live of the power line is by the end of 2023.

Tsachev said the establishment of the new market design is also in the pipeline. He added that the intention is to make it more resilient to market changes.

According to Tsachev, Bulgaria will meet all conditions to become part of the EU common electricity market by 2026.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

eds restructuring tender

Serbia’s distribution system operator plans comprehensive restructuring

30 October 2025 - EDS has launched a tender to select a consultant to develop a restructuring plan and support its implementation

serbia market coupling seepex milos mladenovic

Serbia eyes last quarter of 2027 for power market coupling with EU – SEEPEX CEO

30 October 2025 - Miloš Mladenović was one of the speakers at the 14th International Forum on Energy for Sustainable Development in Skopje

Margun Energy licenses potential 505 MW geothermal power plants

Margün Energy takes over licenses for potential 505 MW in geothermal power plants

30 October 2025 - Margün Energy acquired nine geothermal licenses in Turkey, targeting 3.86 TWh of annual electricity production

First section of cibuk 2 wind park Serbia trial operation

First section of Čibuk 2 wind park in Serbia begins trial operation

29 October 2025 - Masdar and Taaleri Energia generated the first megawatt-hours in their Čibuk 2 wind power plant in Serbia