News

Chronic delays in four green power projects

Published

May 17, 2016

Comments

comments icon

0

Share

Published:

May 17, 2016

Comments:

comments icon

0

Share

Out of six major energy endeavours stuck in development in Macedonia, three are in the area of hydropower and one is for a gigantic photovoltaic facility at Bitola, according to an analysis published by Build.mk portal. The solar power plant project in the south of the country was started in 2010 with work on a feasibility study. French consulting company Sogreah-Carbonium was hired for plans for 39 hectares of land intended for the installation of panels with an overall capacity of 225 MW, equivalent to one unit of the local thermal power plant. The last update on the Bitola system was in 2012, the article said.

The only bigger project completed so far is wind power plant Bogdanci. On the other hand, the development of Boškov most hydropower plant in the northwest has been completely frozen as of lately due to legal and environmental issues. State-owned utility ELEM signed an agreement on a loan with the European Bank for reconstruction and development (EBRD) in late 2011. An adjacent project a hydopower station of Lukovo pole with the capacity of 5 MW is four years overdue, as the tender hasn’t even been published.

The final obsolete power production plan in the list includes hydropower projects Čebren and Galište in the south of Macedonia, with a combined capacity of 500 MW or above. The documentation dates from the times of Yugoslavia and there were a dozen public procurement processes for concession, to no avail.

Related Articles

world dnv energy transition energy transition outlook 2025

Policy changes in US will have marginal impact on global energy transition

09 October 2025 - AI energy use may seem alarming, but it is projected to stay below EV charging and the cooling of buildings, DNV calculated

Bulgaria BEH direct link Black Sea cable participate project

Bulgaria’s BEH wants direct link to future Black Sea cable to participate in project

09 October 2025 - CEO of BEH Valentin Nikolov hinted that Bulgaria would opt for an electricity corridor via Turkey if the proposed cable under the Black Sea doesn't include a direct link to his country

serbia india ChemVolt Global ElevenEs

Indian ChemVolt Global, Serbian ElevenEs forge strategic partnership for batteries

08 October 2025 - India-based ChemVolt Global and ElevenEs, headquartered in Serbia, established a strategic partnership

turkey teias world bank loan Humberto Lopez Orhan Kaldirim Alparslan Bayraktar

Turkey’s TEİAŞ signs USD 750 million loan contract with World Bank

08 October 2025 - A USD 750 million loan will be used for the Transforming Power Transmission System Project, Turkey’s transmission system operator TEİAŞ said