Kalyon hires supplier for rest of Turkey’s largest solar park

Kalyon supplier Turkey largest solar park

Photo: GE Renewable Energy

Published

September 28, 2021

Country

Comments

comments icon

0

Share

Published:

September 28, 2021

Country:

Comments:

comments icon

0

Share

After GE Renewable Energy commissioned the first phase of the Karapınar solar power plant, which has a direct current capacity of 267 MW, Kalyon decided to order its equipment for the remaining 1.08 GW of the project.

Turkish company Kalyon started producing electricity at the first phase of its Karapınar solar power plant in June. At 267 MW of direct current capacity, it is already the biggest facility of its kind in the country, but the entire complex will have 1.35 GW when it is finished, which would currently place it in the top ten on a global scale.

GE Renewable Energy, which delivered its FlexInverter technology for the first part, announced it was also hired for the remaining 1.08 GW. The containerized turnkey system comprises an inverter, a medium voltage transformer, optional medium voltage ring main unit or RMU and auxiliary transformer.

Karapınar solar power plant has three parts

Kalyon is producing its own solar panels at a factory in Ankara. The company built it with state support, while the Karapınar project was won in 2017 under Turkey’s Renewable Energy Resources Area (YEKA) scheme. The combined investment is worth USD 1.4 billion. The factory reached an annual capacity of 1.2 GW.

Kalyon’s solar panel factory in Ankara reached an annual capacity of 1.2 GW

Of note, 1.35 GW in direct current (DC) capacity translates to 1 GW in alternating current (AC), which is the maximum that the solar power plant in Konya province south of the capital will be able to deliver to the transmission network.

The deal for GE Renewable Energy, General Electric’s division based in Paris, is split into two phases: the 270 MW Karapınar II-A and the 810 MW Karapınar II-B. All three sites are in the same area.

Localizing production for project

It is the first time that FlexInverter technology was implemented outside of the United States. GE Renewable Energy is responsible for the design, engineering, project management, site management and commissioning.

Turkey is strict in demanding a high share of domestically-made equipment in renewable energy projects. GE Renewable Energy said it would produce some of the elements in the country.

The entire project is scheduled to be completed by December of next year.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Green for Growth Fund financial impact targets 2023

Green for Growth Fund tops its financial, impact targets in 2023

15 July 2024 - The Green for Growth Fund kept mitigating climate change and promoting sustainable economic growth last year in its 18 markets

IRENA La Camera renewables must grow higher speed scale

IRENA’s La Camera: Renewables must grow at higher speed, scale

12 July 2024 - IRENA's Director-General Francesco La Camera warned of ongoing patterns of concentration in geography in renewables deployment as well as against complacency

green steel electric vehicles study transport environment

Switching to green steel would add just EUR 8 per electric vehicle by 2040

11 July 2024 - Switching to 40% green steel would add just EUR 57 to the sticker price of an electric vehicle in 2030, according to an analysis by T&E

Albania declares eight winners at 300 MW solar power auction

Albania declares eight winners at 300 MW solar power auction

10 July 2024 - The lowest bid at Albania's solar power auction came in at EUR 39.7 per MWh, against a starting level of EUR 59.97 per MWh