Small hydro facilities under environmental review

Published

February 24, 2016

Comments

0

Share

Published:

February 24, 2016

Comments:

0

Share

National Environment Guard, the National Administration Romanian Waters (ANAR) and the National Agency for Environmental Protection (ANPM) were assigned to check small hydropower plants in the country, according to Cristiana Pașca – Palmer, minister of environment, waters and forests. A total of three hundred facilities were installed with the capacity of a maximum of 10 MW, she told Realitatea TV, Agerpres reported.

The sector was booming with not so strict regulation until in 2012 the National Energy Strategy limited the pace, according to the minister. She insisted that, even though she is a proponent of sustainable energy, the impact on biodiversity must be determined. If the environmental costs are bigger than the benefits, the approach must be altered, Pașca – Palmer stressed and added she believes there were breaches of rules.

The environmental permits will be reviewed for compliance, according to the plan. The minister revealed there are six pending applications for permits and that investment in the segment is lower than earlier.

 

Related Articles

europe flexibility seasonal balancing iea report

Flexibility needs to be met by demand response, batteries, hydrogen, but also thermal, hydropower plants – IEA

03 May 2024 - The report Managing the Seasonal Variability of Electricity Demand and Supply analyzes the situation in Europe, India, and Indonesia

Artificial intelligence can detect the toxicity of chemicals

Artificial intelligence can detect toxicity of chemicals

03 May 2024 - Swedish scientists have developed a method using artificial intelligence (AI) to identify toxic chemicals based solely on knowledge of their molecular structure

IPTO suspends all electricity imports until May 7 to protect the Greek system

Greece suspends electricity imports until May 7 to protect system

03 May 2024 - The Greek Independent Power Transmission Operator (IPTO) has announced the suspension of all electricity imports during the hours around noon

drina-hydropower-plants

Court annuls environmental permit for Drina hydropower project

02 May 2024 - The construction of large hydropower plants on the Drina is facing new delays, after a court ruling to scrap the environmental permit for HPP Foča