Solar Energy Group to build 150 MW photovoltaic plant in Kosovo*

Solar Energy Group 150 MW photovoltaic Kosovo

Photo: KOSTT

Published

March 1, 2021

Country

Comments

comments icon

1

Share

Published:

March 1, 2021

Country:

Comments:

comments icon

1

Share

Solar Energy Group signed an agreement with the Transmission, System and Market Operator (KOSTT) of Kosovo* for the connection of its planned 150 MW solar power plant to the grid.

The Transmission, System and Market Operator (KOSTT) of Kosovo* said its Chief Executive Officer Mustafë Hasani (pictured left) signed a deal on connecting a 150 MW photovoltaic plant to the grid with head of Solar Energy Group Europe Egbert Schnuse.

The projected generating capacity is 136 MW in terms of alternating current, while the nameplate capacity is the peak in direct current, the statement reveals.

Solar Energy Group plans to install the plant in the municipality of Gjakova, and production is expected to start in 2022, KOSTT said. It is one of the biggest photovoltaic stations in the pipeline in the Western Balkans region.

The operator added the facility would be connected to the 110 kV transmission network by a new 6.5-kilometer line to the 110/35 kV Gjakova 1 substation.

* This designation is without prejudice to positions on status and is in line with UNSCR 1244/99 and the ICJ Opinion on the Kosovo declaration of independence.
Comments (1)
Ismail Llazani / August 15, 2023

Hi , I have 9.5 acres (4 hectares ) in Topliqan Lipjan Kosovo and I am interested to rent for solar panels if you are interested.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

How to choose a BESS integrator for utility-scale solar projects

31 March 2026 - Solar developers need to consider four main factors when selecting the integrator for a battery energy storage system (BESS)

croatia ancala biomass karlovac plant

Ancala acquires three biomass plants in Croatia

31 March 2026 - Independent infrastructure manager Ancala has acquired three biomass plants from Sherif Group in Croatia

Several Greek hydrogen projects included in ENTSO-G's new development plan

Several Greek hydrogen projects in ENTSO-G’s new development plan

31 March 2026 - Seven Greek natural gas and hydrogen projects have been included in ENTSO-G's new ten-year development plan

Rezolv Energy landmark cross border VPPA giant wind park Vifor

Rezolv Energy signs landmark cross-border VPPA for its giant wind park Vifor

30 March 2026 - Etem Gestamp is sourcing electricity for its operations in Bulgaria from Rezolv Energy’s 461 MW Vifor wind farm in Romania