Interconnection between Macedonia and Serbia set into operation

Published

January 22, 2016

Comments

comments icon

0

Share

Published:

January 22, 2016

Comments:

comments icon

0

Share

A new 70 kilometre long 400 kV line connecting the power systems of Macedonia and Serbia was launched. The EUR 11 million investment is a strategic project of MEPSO (Electricity Transmission System Operator of Macedonia) to improve the safety of the national and regional energy networking, the government in Skopje said.

The ceremony of setting the line from Štip in Macedonia to Vranje in Serbia into operation was attended by MEPSO’s general manager Siniša Spasov and EMS Serbia’s executive manager for system and market operation Branko Šumonja. The new line will improve security, reliability and operability of the wider region and create conditions for larger amount of electricity exchange, Spasov said. Constant upgrading of the security of the national power system and advancing the connections with neighboring energy system operators are MEPSO’s top priorities, he added.

Šumonja said Serbia’s power grid operator EMS invested a total of EUR 50 million from donations and own funds in the transmission line Niš–Leskovac–Vranje–Štip. Macedonia’s Government has invested EUR 50 million in new power lines and renewing the existing power transmitting network, said Vladimir Peševski, vice-premier for economic affairs. The implementation of the interconnection project, supported by the World Bank, is rather significant for Macedonia, as it now connects the country with four neighbors via five lines, he added.

Related Articles

Electrica install 500 MW solar park Liberty Galați steel plant in Romania

Electrica to install giant solar park with storage at Liberty Galați steel plant in Romania

26 February 2026 - Electrica agreed with inactive steel plant Liberty Galați to jointly develop solar power and energy storage capacities of up to 500 MW

north macedonia just transition employees training bitola

Over 600 workers in North Macedonia complete training under just transition projects

26 February 2026 - The projects are part of North Macedonia's Just Transition Investment Platform, launched in 2023, launched by the government

Greek IPTO postpones new island interconnections, proposes higher revenue limit

Greece’s IPTO postpones island interconnections, proposes higher revenue limit

26 February 2026 - New power interconnections between mainland Greece and the Dodecanese and Northern Aegean islands have been...

eu russia natural gas ban energy community

EU decision to ban Russian gas is legal grey zone from Energy Community’s perspective

26 February 2026 - The Energy Community Secretariat is organizing the Vienna Forum on European Energy Law, in partnership with Kinstellar