Ministry’s assessment for wind park annulled

Published

January 15, 2016

Comments

comments icon

0

Share

Published:

January 15, 2016

Comments:

comments icon

0

Share

The Administrative Court in Split accepted Association BIOM’s law suit and declared invalid the decision of Croatia’s Ministry of Environmental and Nature Protection to accept the construction of Bila Ploča wind power plant in Pelješac peninsula in the country’s south. This is the first ruling which blocks a project in an area significant for bird protection as it has been determined that the environmental impact assessment study was unfounded, BIOM said. According to its press release, studies have been produced unprofessionally for years, including findings related to the Natura 2000 network.

The process was initiated by the association and the Croatian Society for Bird and Nature Protection three years ago and the court issued the ruling on December 28. The situation with the study was absurd as state institutions had identified the area as significant for bird protection on an international level, said Vedran Lucić, spokesman of BIOM, and added that bad positioning of wind power plants can cause high mortality of birds and bats, as they collide with turbine blades.

Unfounded studies are the consequence of direct deals between investors and producers of the document, and the ministry tolerates actions against protected species and habitats in Croatia, the press release said. BIOM has three more pending law suits related to bird protection, for wind parks in the mountains of Dinara and Velebit.

Related Articles

masdar socar green solar power projects azerbaijan

Masdar, SOCAR join forces on 760 MW of solar in Azerbaijan

23 November 2024 - Masdar and SOCAR Green have reached financial close for the 445 MW Bilasuvar and 315 MW Neftchala solar projects in Azerbaijan

wind farm ljubusa tomislavgrad

Concession signed for 80 MW wind farm in Tomislavgrad

22 November 2024 - Alpha Wind has been granted a concession to build the 80 MW Ljubuša wind farm in the municipality of Tomislavgrad.

zagreb waste management center tomasevic

Zagreb picks technological solution for city’s waste management system

22 November 2024 - The city has selected technological solution C, one of three proposed, based on an analysis of municipal waste processing technologies

Dentons advises EnergoNuclear EPCM deal Cernavoda

Dentons advises EnergoNuclear on EPCM deal for Cernavodă project

22 November 2024 - Dentons advised EnergoNuclear on an engineering, procurement, and construction management (EPCM) contract for Cernavodă 3 and 4