The Administrative Court in Split accepted Association BIOM’s law suit and declared invalid the decision of Croatia’s Ministry of Environmental and Nature Protection to accept the construction of Bila Ploča wind power plant in Pelješac peninsula in the country’s south. This is the first ruling which blocks a project in an area significant for bird protection as it has been determined that the environmental impact assessment study was unfounded, BIOM said. According to its press release, studies have been produced unprofessionally for years, including findings related to the Natura 2000 network.

The process was initiated by the association and the Croatian Society for Bird and Nature Protection three years ago and the court issued the ruling on December 28. The situation with the study was absurd as state institutions had identified the area as significant for bird protection on an international level, said Vedran Lucić, spokesman of BIOM, and added that bad positioning of wind power plants can cause high mortality of birds and bats, as they collide with turbine blades.

Unfounded studies are the consequence of direct deals between investors and producers of the document, and the ministry tolerates actions against protected species and habitats in Croatia, the press release said. BIOM has three more pending law suits related to bird protection, for wind parks in the mountains of Dinara and Velebit.

Related Articles

eu western balkans cbam electricity market amendments

EU’s amendments to CBAM: possibility of relief, but January 1 brought market uncertainty

06 January 2026 - Long-awaited implementing acts and amendments to the CBAM Regulation brought only a minor relief for...

After adding PV unit Slovenian gas power plant TEB battery project

After adding PV unit, Slovenian gas power plant TEB launches battery project

06 January 2026 - The management of the Brestanica gas power plant has decided to diversify its activities further with a battery energy storage system

D Trading offtake 200 MW solar PPA with Econergy Romania

D.Trading to offtake 200 MW of solar in PPA with Econergy in Romania

06 January 2026 - DTEK Group's D.Trading signed an offtake deal with Econergy for 200 MW of solar power in Romania, including the country's largest PV plant

montenegro TSO cges investments ranko redzic

Montenegro’s TSO CGES to invest EUR 200 million

05 January 2026 - Montenegrin TSO CGES plans to invest EUR 200 million, according to Ranko Redžić, manager of the company's national dispatching center