Cretan interconnection plan scaled back

Published

December 21, 2015

Comments

comments icon

0

Share

Published:

December 21, 2015

Comments:

comments icon

0

Share

The Independent Power Transmission Operator (IPTO or Admie SA) cut back on the scale of its interconnection plan intended to link Crete with the grid serving the wider Athens area and, for the time being, will connect the island as far north as the Peloponnese, according to sources of Energy Press portal.

The operator is striving to finalize the revised latter project’s details for inclusion in its ten-year plan, the report said. The initial plan, offering a capacity of 1 GW, would have covered electricity supply needs from the mainland to Crete, while also serving as a channel for the supply of the island’s renewable energy production from to the capital city’s area.

Following the revision, the project will, for its initial stage, be limited to a 2 x 200 MW system connecting the Peloponnese with Crete to cover the island’s electricity needs. The resulting infrastructure will not be able to facilitate delivery of Cretan green power production to Athens. This will require development of a supplementary project, according to Energy Press.

Related Articles

Ember Warming 2024 global power demand rise with fossil fuels

Ember: Warming’s 2024 share of global power demand rise was covered with fossil fuels

09 April 2025 - Renewables and nuclear energy met 79,1% of 2024 global power demand growth. The fossil fuels share was bigger than the part attributed to the annual rise in temperatures.

delta green scheme flexibility households grid balancing

Delta Green launches platform in CEE for households to provide grid balancing

09 April 2025 - Delta Green claims it is the first in Central and Eastern Europe and among the first in Europe to implement such a solution

EUSEW2025, Registration open for the European Sustainable Energy Week

EUSEW 2025: Registration open for the European Sustainable Energy Week

09 April 2025 - Applications are open for participation in the 19th annual European Sustainable Energy Week - EUSEW 2025, which will be held from June 10 to 12.

Activists northeastern BiH obstruct Majevica lithium mining project

Activists in northeastern BiH to obstruct Majevica lithium mining project

09 April 2025 - Arcore and Rock Tech Lithium are planning to excavate and process lithium, boron and magnesium in Majevica in northeastern BiH