HEP starts trial of Korlat, first unsubsidized wind farm in Croatia

HEP Korlat commercial wind Croatia

Photo: HEP

Published

May 11, 2020

Country

Comments

comments icon

0

Share

Published:

May 11, 2020

Country:

Comments:

comments icon

0

Share

The first wind power plant built by the national power producer is scheduled to enter full operation in August. HEP finished the construction of Korlat, the biggest wind park in Croatia, and connected it to the grid for a test run.

Croatian Energy Market Operator Ltd. (HROTE) has announced it signed a contract with wind power plant Energetski park Korlat doo and temporarily included it in the electric power system. The 58 MW facility thus began its trial run, which is planned to last until August. When Hrvatska elektroprivreda or HEP Group commissions Korlat, it is set to be the first wind park in Croatia operating without feed-in tariff incentives.

Estimated annual output is 170 GWh. The project near Benkovac in Dalmatia cost more than HRK 500 million (EUR 66.1 million). It consists of 18 turbines of 3.6 MW each, so the connection capacity is 10.5% below the maximum.

The towers are 114 meters high and Nordex SE’s machines have a diameter of 131 meters. Ing-grad doo was responsible for infrastructure and the grid connection and Fractal doo was hired for construction and supervision.

HEP aims to boost its wind and solar power portfolios to 350 MW each by 2030. It has revealed plans to add a 75 MW photovoltaic unit at the Korlat site. It is the biggest wind park in Croatia so far and the company’s first system of its kind.

Nordex has a 20-year service and maintenance deal.

Kelag-Kärntner Elektrizitäts’ subsidiary Interenergo put into operation a 10 MW wind power plant in nearby Jasenice in January. The Government of Croatia has been accelerating the efforts to lift the share of energy from renewable sources.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

north macedonia batteries BESS solar wind natural gas investments sanja bozinovska

North Macedonia receives applications for 4,172 MW of battery projects

10 October 2025 - October 1 was the deadline for foreign investors interested in the construction of power plants to submit their initiatives

Greek regulator steps in to prevent energy communities abuse

Greek regulator steps in to prevent energy communities misuse

10 October 2025 - Legitimate energy communities have suffered in Greece, as private investors have been taking advantage of the status

CJR Renewables 102 MW Urleasca wind farm Romania

CJR Renewables completes construction of 102 MW Urleasca wind farm in Romania

09 October 2025 - The Urleasca wind farm in Brăila county in eastern Romania is complete, contractor CJR Renewables said

world dnv energy transition energy transition outlook 2025

Policy changes in US will have marginal impact on global energy transition

09 October 2025 - AI energy use may seem alarming, but it is projected to stay below EV charging and the cooling of buildings, DNV calculated