HEP starts trial of Korlat, first unsubsidized wind farm in Croatia

HEP Korlat commercial wind Croatia

Photo: HEP

Published

May 11, 2020

Country

Comments

comments icon

0

Share

Published:

May 11, 2020

Country:

Comments:

comments icon

0

Share

The first wind power plant built by the national power producer is scheduled to enter full operation in August. HEP finished the construction of Korlat, the biggest wind park in Croatia, and connected it to the grid for a test run.

Croatian Energy Market Operator Ltd. (HROTE) has announced it signed a contract with wind power plant Energetski park Korlat doo and temporarily included it in the electric power system. The 58 MW facility thus began its trial run, which is planned to last until August. When Hrvatska elektroprivreda or HEP Group commissions Korlat, it is set to be the first wind park in Croatia operating without feed-in tariff incentives.

Estimated annual output is 170 GWh. The project near Benkovac in Dalmatia cost more than HRK 500 million (EUR 66.1 million). It consists of 18 turbines of 3.6 MW each, so the connection capacity is 10.5% below the maximum.

The towers are 114 meters high and Nordex SE’s machines have a diameter of 131 meters. Ing-grad doo was responsible for infrastructure and the grid connection and Fractal doo was hired for construction and supervision.

HEP aims to boost its wind and solar power portfolios to 350 MW each by 2030. It has revealed plans to add a 75 MW photovoltaic unit at the Korlat site. It is the biggest wind park in Croatia so far and the company’s first system of its kind.

Nordex has a 20-year service and maintenance deal.

Kelag-Kärntner Elektrizitäts’ subsidiary Interenergo put into operation a 10 MW wind power plant in nearby Jasenice in January. The Government of Croatia has been accelerating the efforts to lift the share of energy from renewable sources.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Over 20,000 prosumer projects connected in Greece during last 18 months

Over 20,000 prosumer units connected in Greece in last 18 months

24 July 2025 - Households and businesses remain highly interested in becoming prosumers in Greece, although the new net billing program faces delays.

Project 81 MW solar park on coal mine in Montenegro

Project underway for 81 MW solar park on coal mine in Montenegro

24 July 2025 - The Government of Montenegro gave a provisional green light for a solar power plant of 81.1 MW in peak capacity on coal land in Pljevlja

croatia rp global novalja solar ebrd loan

RP Global gets EUR 12.2 million loan for Novalja solar project

24 July 2025 - In late April, Austrian company RP Global began the construction of the Novalja PV plant at the Zaglava site on the island of Pag

solarpower europe report 2025

EU faces first annual solar installation decline since 2015 – report

24 July 2025 - The EU is set to install less new solar in 2025 than it did in 2024 - the first annual drop in a decade, according to SolarPower Europe