The cabinet warned high fines are inevitable if the country misses its targets for electricity generation from renewables. Slovenia vowed to remove administrative barriers for investors who install small green power units. The new bylaw excludes units for self-consumption.

Based on the provisions of last year’s Energy Act, a new decree in Slovenia has regulated the category of small green power facilities and devices. They produce electricity from renewable sources and in high-efficiency cogeneration. Advanced combined units for heat and power with the capacity of 50 kW at most, solar power plants of a maximum of 1 MW and wind turbines not stronger than 50 kW don’t require a building permit, the government said.

The bylaw comes into force on March 21. The cabinet determined it applies to simple systems mounted on or located next to existing structures. Units for self-consumption were excluded.

Slovenia must achieve binding targets for electricity generation from renewables or it will face high fines, the cabinet warned in the statement. It vowed to support the installation of the said small green power and high-efficiency cogeneration devices by eliminating administrative barriers.

According to the specifications, the device can’t take up more than one fifth of the building’s surface. The height of a wind turbine placed on a tower on the foundation of the structure can’t be over ten meters. If the pole is on the building, total height mustn’t exceed half of the building’s height.

Fines for breaking the rules are between EUR 250 and EUR 25,000, depending on if the investor is an individual, a legal entity or its representative. The highest possible penalty is for large companies.

The order notes obligations regarding the static, fire safety, lightning risk and noise protection assessments. The government of Slovenia said the investor must obtain consent from the owner of the adjacent land if the small green power system is planned to be installed less than 1.5 meters from the line.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Energy companies confront dual mandate keeping supply secure while accelerating green transition BEF 2026

Energy companies in Western Balkans confront dual mandate – keeping supply secure while accelerating green transition

13 May 2026 - Companies in the region have challenges in energy security, decarbonization and digitalization, and the key is investing in production, the grid and batteries, according to the panel on power system transition at Belgrade Energy Forum 2026

serbia eu region bef 2026 jelena matejic ems renewables grid connection

Matejić: Serbia’s grid to integrate 12 GW of renewables in next six years

12 May 2026 - Jelena Matejić, General Manager of Elektromreža Srbije, took part in a panel on transmission grids at Belgrade Energy Forum 2026

Belgrade Energy Forum 2026 EU support necessary decarbonization Western Balkans

Belgrade Energy Forum 2026: EU’s support necessary for decarbonization in Western Balkans

11 May 2026 - The Western Balkans have progressed in decarbonization and integration with the EU's single energy market, but it must add speed, and with EU's help, top officials agreed at Belgrade Energy Forum 2026 in Serbia

Montenegro EPCG trial run of first wind park Gvozd

Montenegro’s EPCG starts trial run of its first wind park – Gvozd

10 May 2026 - EPCG launched the trial operation of its first wind power plant. Gvozd would be the biggest in Montenegro when the second phase is completed.