Hidroelectrica, the largest electricity producer in Romania, announced the opening of its hydroelectric power plant in Hunedoara for December.

The facility is on the Strei river in Transylvania and is presently 62% complete, portal Business-review.eu reported. The EUR 58 million investment is for 12 MW of installed power capacity. Overall, the still insolvent state-owned company is planning to build up to seven hydroelectric power plants on the Strei river, which would require an estimated investment of EUR 420 million. Between 2012 and 2014 Hidroelectrica has invested over EUR 270 million in new power plants, according to company data.

The utility set an investment budget of EUR 1.3 billion for 2015–2020. Hidroelectrica went into insolvency in 2012 following a severe drought and several loss-making contracts which generated a combined loss of USD 1.4 billion. After it underwent a restructuring process the company turned to profit and exited insolvency in 2013, but was forced back into insolvency the following year at the request of contract holders. Following an in-depth investigation, the European Commission said in June that electricity supply contracts signed by Hidroelectrica did not involve state aid within the meaning of the EU rules.

Hidroelectrica recorded a profit of RON 725 million (EUR 161.9 million) from the first six months of this year, 42% more than in the corresponding period of last year. Turnover was also higher by almost EUR 67.77 million year on year. The increase was due to an output of 9.6 TWh, compared to 8.5 TWh in the same period last year.

Related Articles

Major offshore wind projects shelved in another blow to industry

Major offshore wind projects shelved in another blow to industry

09 May 2025 - Ørsted decided to halt its Hornsea 4 project in the UK, while the US stopped the construction of Equinor's Empire Wind 1 facility

Serbia EPS PPAs wind parks Alibunar 1 Alibunar 2

Serbia’s EPS signs PPAs for wind parks Alibunar 1, Alibunar 2

08 May 2025 - Serbia's state-owned Elektroprivreda Srbije will offtake electricity from future wind parks Alibunar 1 and Alibunar 2, of 168 MW in total.

Serbia’s TSO EMS signs grid connection contracts for 11 renewable power plants

08 May 2025 - TSO Elektromreža Srbije said the contracts were signed after the second interval for the preparation of grid connection studies

Europe record battery storage capacity growth 2024 expansion slows

Europe has record battery storage capacity growth in 2024 but expansion slows

08 May 2025 - The leap in new battery storage capacity in Europe last year wasn't as impressive as in the previous years