Hidroelektrane na Trebišnjici completes overhaul

Published

July 13, 2015

Comments

0

Share

Published:

July 13, 2015

Comments:

0

Share

Planned annual maintenance of Bosnian hydropower producer Hidroelektrane na Trebišnjici was completed on schedule and the producer is back on stream, SeeNews said, citing local media reports.

Total cost of the 40-day overhaul was BAM 100,000 (EUR 51,100), news agency Srna reported. Hidroelektrane na Trebišnjici, comprising three hydropower plants along the Trebišnjica river, is located in the southern part of the Republic of Srpska, the smaller entity of Bosnia and Herzegovina.

Company official Ljubomir Zotović announced the complete refurbishment of a generating unit in hydropower facility Dubrovnik by the end of October, Srna said.

Related Articles

Turkey-based-Yildirim-109-MW-solar-park-Kosovo-ferronickel

Turkey-based Yıldırım building 109 MW solar park in Kosovo* for its ferronickel plant

07 May 2024 - Yıldırım Energy marked the start of construction works on a 150 MW solar farm in Kosovo*. It will supply the group's ferronickel plant.

BIG Mega Renewable Energy secures financing for landmark Urleasca wind farm in Romania

BIG Mega Renewable Energy secures financing for landmark Urleasca Wind Farm in Romania

07 May 2024 - BIG Mega Renewable Energy, a leading renewable energy developer, has successfully secured financing for the construction and operation of its landmark Urleasca Wind Farm in Romania

Afroditi_Psatha

Putting people first: renovate to future-proof Europe’s schools

07 May 2024 - Imagine a future where Europe's schools and educational institutions are transformed into models of energy efficiency, providing our children and teachers with healthier, more comfortable, and more sustainable learning environments

Slovenia coal plant TES close already within three years

Slovenia’s coal plant TEŠ could close already within three years

06 May 2024 - Slovenian Prime Minister Robert Golob said coal plant TEŠ and its accompanying mine may end operations before the expected closure in 2033