Electricity Transmission System Operator of Macedonia (MEPSO) and the consortium of Siemens and SisKon have signed a contract on revitalization of Dubrovo 400/110kV substation, worth EUR 4.6 million. With this project MEPSO starts new investment cycle in revitalization of the network, worth more than EUR 50 million.

At the signing of ceremony held last week in Skopje, Sašo Vasilevski, MEPSO General Director, said that the company’s mid-term investment cycle will start with several substation revitalization projects in Macedonia.

He said that Dubrovo substation project foresees replacement of the primary equipment and revitalization of the secondary equipment. The substation is located in the area of Negotino, a town in central Macedonia, and it is a vital part of the 400kV transmission and interconnection network.

Within the new investment cycle, MEPSO plans to revitalize several transformer stations, build a new transformer station near Ohrid and seven new transmission lines.

Srdan Srdanović, head of the Siemens’ Energy Management Division for the Adriatic region, who signed a contract as a representative of the consortium, said that Siemens continues the successful cooperation with MEPSO, recalling several implemented substation reconstruction projects.

The Dubrovo substation project will be financed by MEPSO’s funds, a grant of the Western Balkans Investment Framework (WBIF) and a loan from the European Bank for Reconstruction and Development (EBRD).

The revitalization should be completed in three years and provide more safe and reliable high-voltage equipment, real-time monitoring system, timely detection and prevention of damage and optimization of the transmission system management.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

north macedonia kazanci memorandum gas power plant mickoski Cemil Kazancı

North Macedonia, Kazancı sign memorandum on gas power plants

23 July 2025 - The memorandum of understanding was signed by Prime Minister Hristijan Mickoski and Cemil Kazancı, President of the Board of Directors of Kazancı Holding

romania bess battery Nova Power & Gas gas power plant

Nova Power & Gas to install 200 MW BESS in Romania

23 July 2025 - Romanian company Nova Power & Gas is also beginning the construction of a 150 MW gas power plant in Florești, of 150 MW.

IRENA 91 percent new renewables units more cost effective than fossil fuel alternatives

IRENA: 91% of new renewables units are more cost-effective than fossil fuel alternatives

23 July 2025 - Renewables maintained their cost leadership in global power markets, the International Renewable Energy Agency said in an annual report

China based Astronergy solar cell factory western Turkey

China-based Astronergy to build solar cell factory in western Turkey

23 July 2025 - Astronergy allocated USD 700 million for its second solar module factory in Turkey. In the first phase, it would make wafers and cells.